Every state and territory has its own work health and safety law. Seven of them, plus the Commonwealth, copied a shared national model, so the Safe Work Method Statement (SWMS) rules are very close. Victoria runs its own system. Your SWMS should cite the Act, Regulations and regulator for the state where the work is done.
This guide explains what those laws are, how they fit together, where to find the current version for your state, and why they are not all the same.
What are the Act, the Regulations and the Codes?
Work health and safety law comes in three layers. Think of it as: what you must achieve, the detailed rules, and the practical how-to.
- The Act sets the duties. The big one is the primary duty of care: a person conducting a business or undertaking (PCBU) must ensure, so far as is reasonably practicable, the health and safety of its workers and of anyone else affected by the work. The Act also covers officers’ and workers’ duties, consultation, incident notification, inspectors and penalties. It is passed by parliament.
- The Regulations fill in the detail. This is where the SWMS rules are. Under the model Regulations, a SWMS is required for high risk construction work, the 18 categories are listed, and the rules for preparing, following, reviewing and keeping a SWMS are set out. Regulations are made by the government under the Act and are just as binding.
- Codes of Practice explain how to meet the duties in practice, for example the Code of Practice: Construction work. A Code has to be approved in each state before it has any legal effect there. In most places an approved Code is not the law itself, but a court can use it as evidence of what was known about a hazard and what was reasonably practicable. NSW changed this on 1 July 2026: Codes are now the minimum standard you are expected to meet.
Below that sits guidance material from regulators and Australian Standards. These are useful, but they are not law unless the Act, Regulations or a Code calls them up.
What “reasonably practicable” means
Most duties are qualified by “so far as is reasonably practicable”. The model Act says this means what is reasonably able to be done, weighing up how likely the risk is, how bad the harm could be, what you know or ought to know about the hazard and the ways to control it, whether those controls are available and suitable, and, last of all, whether the cost is grossly disproportionate to the risk. Cost alone is not a reason to skip a control.
Why are there different laws in each state?
Workplace safety has always been mostly a state and territory matter. Until 2012 every one of them had its own occupational health and safety (OHS) law, with different duties, terms and rules.
In 2008 the Commonwealth, states and territories agreed to harmonise those laws. Safe Work Australia wrote a model WHS Act, model Regulations and model Codes of Practice. The model laws are a template. They do not apply anywhere until a parliament passes its own version. That happened in stages:
- 1 January 2012: the Commonwealth, ACT, NSW, NT and Queensland
- 1 January 2013: South Australia and Tasmania
- 31 March 2022: Western Australia (passed in 2020)
- Victoria: has not adopted them and keeps its OHS Act 2004.
Even among the adopters, the laws drift apart over time:
- Each state makes its own variations. Some are drafting changes to fit local law; some are real policy differences, such as South Australia’s $450,000 construction project threshold or Western Australia’s headcount test.
- Changes to the model do not flow through automatically. When Safe Work Australia amends the model laws, each parliament or government has to make the change itself, on its own timetable.
- Codes are approved one state at a time. A model Code only applies where it has been approved, and some states have their own Codes or versions.
- Regulations are remade on different cycles. NSW remade its Regulation in 2025, and Tasmania in 2022. Victoria’s 2017 Regulations have been extended to April 2028 while they are remade.
Safe Work Australia publishes a cross-comparison table of the differences between the state Acts and the model Act.
Which laws apply in each state?
Links go to the official legislation register, or to the regulator’s legislation page for NSW.
Commonwealth workplaces covered by Comcare use the Commonwealth WHS Act 2011. Mining, electrical safety and dangerous goods often have separate laws and regulators as well. Safe Work Australia keeps a list of every regulator.
The construction project test decides when a job needs a principal contractor and a WHS management plan. See principal contractor duties by state.
How do you find and read the law?
- Use the official register. Each state publishes its legislation free online, with the current in-force version. Check the “as at” or “current from” date. A PDF saved years ago, or a copy on someone else’s website, may be out of date.
- Start with the regulator. Regulators explain the law in plain terms and link to the official text. Their guidance is often the quickest way to the section you need.
- Know the references. “s 19” is section 19 of the Act. “r 299” or “reg 299” is regulation 299. The SWMS rules sit in the construction chapter of the Regulations, in the model version regulations 289 to 303.
- Check your own state’s numbering. The adopting states mostly follow the model’s structure, but not always the same numbers. Quote the version that applies where you work.
- Use the model laws to understand, not to cite. Safe Work Australia’s model Act, model Regulations and model Codes are clear and well explained, but on a document, cite your state’s law.
What is the same for a SWMS everywhere?
Across the WHS states and territories, the core SWMS rules come from the same model Regulations:
- A SWMS is required before high risk construction work starts. The model list has 18 categories, such as falls over 2 metres, trenches deeper than 1.5 metres and powered mobile plant.
- It must identify the work, the hazards and risks, the control measures, and how the controls will be put in place, monitored and reviewed. It must be easy to understand for the people who use it.
- The work must be done in line with it, or stopped.
- On a construction project, the principal contractor gets a copy before the work starts.
- It is reviewed when the controls change, and kept until the work is finished, or for 2 years after a notifiable incident.
For the detail, see what is a SWMS? and keeping, signing and reviewing a SWMS.
What is different for a SWMS?
- The legal references. Each state has its own Act, Regulations, regulator and incident notification line. A SWMS should name the right ones.
- Construction project thresholds. $250,000 or more under the model Regulations and in NSW, the ACT, Queensland and Tasmania; $450,000 or more in South Australia; $1,000,000 or more in the Northern Territory from 28 May 2026 ($500,000 if work began before then); $350,000 or more in Victoria; and in Western Australia, 5 or more people working on site at the same time.
- Codes of Practice. Each state approves its own. In NSW they have been the minimum standard since 1 July 2026. See are Codes of Practice legally binding?
- Specific rules. For example, in the ACT any asbestos removal needs a licence, with no 10 square metre exemption. See asbestos removal SWMS and licences.
- Exposure limits. Workplace Exposure Limits start on 1 December 2026 as each jurisdiction implements them, and Victoria has a longer transition for 15 substances. See what are WES and WEL?
How is Victoria different?
Victoria uses the Occupational Health and Safety Act 2004 and OHS Regulations 2017, regulated by WorkSafe Victoria. A SWMS is still required for high risk construction work, and the basic idea is the same, but:
- the duty holders are employers and self-employed persons, not PCBUs
- it lists 19 types of high risk construction work, not 18
- the SWMS must be reviewed when the work changes, when there is a sign the controls are not working, or after an incident during the work
- a copy is kept for the duration of the work, and hand-written amendments can be made on site
- it has compliance codes rather than approved Codes of Practice
- the principal contractor duties apply to construction projects costing $350,000 or more, and the plan is called a health and safety coordination plan.
A SWMS that cites the WHS Act, a PCBU or a model Code is not written for Victoria, and that is a common reason documents get sent back there. See WorkSafe Victoria’s SWMS guidance.
Do you need a state-specific SWMS?
The hazards in a trench are the same in Perth and Penrith. What changes is the law the SWMS answers to. Use a SWMS that cites the Act, Regulations, regulator and Codes for the state where the work is done, and update the references if you take a document across a border.
Our trade packs are written separately for each state, including Victoria. You pick the state at checkout, and each pack is $249.99 per state, editable Word, one-off purchase. Browse trade packs, or read do I need a SWMS? first. Whichever you use, tailor it to the job before it goes to site: see how to use a SWMS template.
Common questions
Are SWMS requirements the same across Australia?
Mostly. Every state and territory except Victoria has adopted a version of the model Work Health and Safety (WHS) laws, so the core Safe Work Method Statement (SWMS) rules are very similar. Victoria runs its own Occupational Health and Safety (OHS) Act 2004 and OHS Regulations 2017. The details that differ are the Act and regulator you cite, some thresholds, and how Codes of Practice work.
Where do I find the WHS Act for my state?
On your state or territory’s official legislation website, which has the current in-force version. Your regulator’s website also links to it. Safe Work Australia publishes the model laws, but they are not law anywhere until a state adopts them.
What is the difference between the Act, the Regulations and a Code of Practice?
The Act sets the duties, such as the duty to keep workers safe so far as is reasonably practicable. The Regulations set the detail, including when a SWMS is needed and what goes in it. A Code of Practice is practical guidance on how to meet those duties. Codes are approved by each state, and since 1 July 2026 they are enforceable in NSW.
Can I use a SWMS written for another state?
The hazards and controls may carry over, but the legal references usually do not. A SWMS that cites another state’s Act, regulator or Codes can be knocked back by a principal contractor. Update it for the state where the work is done.
Why is Victoria different?
Victoria never adopted the model WHS laws. It kept its OHS Act 2004 and makes its own regulations, with WorkSafe Victoria as the regulator. It still requires a SWMS for high risk construction work, but it lists 19 types of that work, uses “employer” rather than PCBU, and has compliance codes instead of approved Codes of Practice.
Sources: Safe Work Australia—Legislation, Model WHS Act (sections 18, 19, 274 and 275), Model WHS Regulations (regulations 289–303), Safe Work Australia—Codes of Practice, the state legislation registers linked above, and WorkSafe Victoria. General information only; check the current law with your regulator.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.