A Safe Work Method Statement (SWMS) is a document that sets out high risk construction work, the hazards and risks of that work, and how those risks will be controlled. Under the model Work Health and Safety (WHS) Regulations it must be prepared before the work starts, and the work must then be done the way the SWMS says.
What is a SWMS for?
The model Code of Practice: Construction work says the main purpose of a SWMS is to help businesses, supervisors and workers put in place and monitor the controls for high risk work. In plain terms, it makes the crew think the job through before it starts, agree how the dangerous parts will be done, and write that down so everyone works the same way.
A SWMS is not paperwork for the office. It is meant to be read and used at the work area. If the job is not being done the way the SWMS says, the work has to stop.
When is a SWMS required?
A SWMS is required for high risk construction work (HRCW). That takes two tests:
- Is it construction work? The model Regulations define this widely: building, altering, renovating, repairing, maintaining, fitting out, demolishing or dismantling a structure, plus excavation, site preparation and installing or testing services. Some things are left out, such as testing, maintenance or repair work of a minor nature.
- Is it high risk? The Regulations list 18 categories, such as a risk of falling more than 2 metres, a trench deeper than 1.5 metres, powered mobile plant, energised electrical services, asbestos, confined spaces and traffic corridors. See the 18 categories of high risk construction work.
If both answers are yes, you need a SWMS. For other construction work it is not required by law, but you still have to manage the risks. Clients and principal contractors often ask for one anyway. See do I need a SWMS?
What must a SWMS contain?
Under regulation 299 of the model WHS Regulations, a SWMS must:
- identify the work that is high risk construction work
- specify the hazards of that work and the risks to health and safety from them
- describe the control measures that will be used
- describe how the controls will be implemented, monitored and reviewed.
It must also take into account the conditions at the workplace, and on a construction project, the principal contractor’s WHS management plan. And it must be set out so the people using it can understand it.
Most SWMS also include the business and principal contractor details, the work location, the person responsible for checking the SWMS is followed, the plant, licences and permits involved, the date, and a sign-on section. Safe Work Australia’s SWMS information sheet has a simple template that shows the layout.
What makes a SWMS good or bad?
The Construction Code is blunt about this. A SWMS should give clear direction, with no statements that leave the decision to a supervisor or worker. “Use appropriate PPE” is its example of what not to write. Say which PPE, when.
- Specific to the site. A generic SWMS can be used for work you do regularly, but it must be reviewed for each workplace and changed where needed.
- Controls in the right order. Work down the hierarchy of controls: eliminate the hazard if you can; if not, substitute, isolate or use engineering controls; then administrative controls such as procedures, training and signs; and personal protective equipment (PPE) last. A SWMS that relies mainly on PPE usually needs more work.
- Readable. The Code says to consider the crew’s literacy and language. Shorter and clearer beats longer.
- Built with the crew. Workers and their health and safety representatives must be consulted when it is prepared.
For the method, see how to write a SWMS. For the common reasons one gets sent back, see how to review a subcontractor’s SWMS.
Who prepares a SWMS?
The person conducting a business or undertaking (PCBU) that carries out the high risk construction work. On a typical job that is the contractor or subcontractor doing the task, not the builder above them. The Code says the person carrying out the work is best placed to prepare it, in consultation with the workers who will do it.
If two businesses share the same high risk work, for example a roof plumber and the crane crew lifting the sheets, they must consult and agree who prepares the SWMS. They can use one SWMS or one each.
A principal contractor does not write every subcontractor’s SWMS, but must get a copy before the work starts and should check the work is done to it.
How is a SWMS used on site?
- Brief the crew before work starts. Everyone should know the controls, and that work stops if the SWMS is not followed.
- Sign on. The law does not require signatures, but most sites do, and they are your evidence of the briefing.
- Keep it at the work area, or where it can be got to quickly. Electronic copies are fine if the crew can open them.
- Watch the work. If the job is not being done the SWMS way, stop it and do not restart until it is.
- Review it when the controls change, and in practice whenever the method, site, crew or conditions change, or after an incident.
- Keep it until the work is finished, or for 2 years after a notifiable incident.
The detail is in keeping, signing and reviewing a SWMS.
SWMS, JSA, SOP and risk assessment: what is the difference?
A SWMS is the legal document for high risk construction work. A Job Safety Analysis (JSA) breaks any task into steps and is good practice, but it is not a legal requirement and does not replace a SWMS. A Safe Operating Procedure (SOP) is a step-by-step guide to using a piece of plant or doing a routine task. A risk assessment is the thinking behind all of them. See SWMS vs JSA.
Is a SWMS the same in every state?
Close, but not the same. Every state and territory except Victoria has adopted the model WHS laws, so the core SWMS rules match. Victoria requires a SWMS under its own OHS Regulations 2017, with 19 types of high risk construction work and its own review rules. The Act, regulator and Codes a SWMS refers to should match the state where the work is done. See SWMS requirements by state.
How do you get a SWMS?
You can write one from scratch. That is fine for one or two tasks, but it is a lot of work to do properly for everything your trade does. Most businesses start from a template written for their trade and state, then add the site, crew and job details. See how to use a SWMS template.
Our trade packs include every SWMS for the trade, written for your state, in editable Word, plus the SOP pack. Each is $249.99 per state, one-off purchase. Not sure which fits? See which SWMS pack do I need?
Common questions
What does SWMS stand for?
Safe Work Method Statement. It is a document that sets out the high risk construction work being done, the hazards and risks of that work, the controls that will be used, and how those controls will be put in place, monitored and reviewed.
Is a SWMS a legal requirement?
Yes, for high risk construction work. Under the model Work Health and Safety (WHS) Regulations, a SWMS must be prepared before high risk construction work starts. For other construction work a SWMS is not required by law, but the risks still have to be managed, and many sites ask for one anyway.
Who prepares a SWMS?
The person conducting a business or undertaking (PCBU) carrying out the high risk construction work, usually the contractor or subcontractor doing the job. It should be prepared with the workers who will do the work. On a construction project, a copy goes to the principal contractor before work starts.
Does a SWMS need to be signed?
The model regulations do not say a SWMS must be signed. The Construction Code says it may include the names and signatures of the workers consulted, and most principal contractors require a sign-on before work starts. A signature is evidence the crew was briefed.
Can one SWMS cover more than one task?
Yes. The Construction Code says one SWMS can cover several types of high risk construction work at the same workplace, or you can prepare a separate SWMS for each. If you use separate ones, check the controls do not conflict.
Sources: Model WHS Regulations (regulations 289, 291 and 299–303), Model Code of Practice: Construction work, Safe Work Australia SWMS information sheet and WorkSafe Victoria—SWMS. General information only; check the law in your state with your regulator.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.