Under the model WHS Regulations, a Safe Work Method Statement (SWMS) must be prepared before high risk construction work (HRCW) starts. The work must follow it, or stop. On a construction project, a copy goes to the principal contractor before the work starts. The SWMS is reviewed when the controls change, and kept until the work is finished, or for at least 2 years after a notifiable incident.
This guide is for the business that prepares and uses the SWMS. If you are a principal contractor checking a subcontractor’s SWMS, see how to review a subcontractor’s SWMS. For what a SWMS is and how to write one, see what is a SWMS? and how to write a SWMS.
The five rules in the model WHS Regulations
Regulations 299 to 303 of the model WHS Regulations set out the SWMS duties of a person conducting a business or undertaking (PCBU) that carries out HRCW.
- Prepare it before the work starts (r 299). The SWMS must identify the HRCW, specify the hazards and risks, describe the control measures, and describe how they will be implemented, monitored and reviewed. It must take account of the workplace’s circumstances and, on a construction project, the principal contractor’s WHS management plan. It must be easy for the people who use it to understand.
- Work to it (r 300). Put arrangements in place to make sure the HRCW is done in line with the SWMS. If it is not, stop the work immediately or as soon as it is safe to, and do not restart until it can be done in line with the SWMS.
- Give a copy to the principal contractor (r 301). If the HRCW is part of a construction project, the principal contractor must have a copy before the work starts.
- Review it (r 302). Review the SWMS, and revise it as necessary, whenever the relevant control measures are revised.
- Keep it (r 303). Keep a copy until the HRCW is completed. If a notifiable incident occurs in connection with the work, keep it for at least 2 years after the incident. While it is kept, it must be readily accessible to the workers doing the work and available for inspection.
Each state and territory under the WHS laws has adopted these in its own regulations, so check yours. A construction project is defined by a cost threshold in most places, and the figure is not the same everywhere. See principal contractor duties by state.
When should you review a SWMS?
The legal trigger in the model WHS Regulations is a change to the control measures. In practice that happens more often than people think. Review the SWMS when:
- the method, plant, materials or crew change
- the site conditions change, for example weather, ground conditions, access or other trades working nearby
- a control is not working, or work had to stop because it did not match the SWMS
- there has been an incident or near miss
- the principal contractor’s WHS management plan or site rules change
- workers or their health and safety representative raise a concern.
The model Code of Practice: Construction work says workers and their health and safety representatives must also be consulted when a SWMS is reviewed, and that every version should be kept when it is revised.
Who signs a SWMS?
The model WHS Regulations do not say a SWMS must be signed. But signing is common for good reasons:
- The Construction Code says a SWMS may include the workers consulted, the date of consultation, and each worker’s signature acknowledging their part in developing it.
- Safe Work Australia’s SWMS information sheet template has boxes for the reviewer’s signature and for worker signatures.
- Most principal contractors make a signed sign-on a site rule, and will not let work start without it.
A signature is evidence that the crew has been consulted and briefed. It is not a substitute for actually doing that. Sign new workers on when they join the task, and re-brief the crew after a revision.
Where should the SWMS be kept?
Where the workers can get to it. The Construction Code says that if the SWMS is not kept at the workplace, it should be somewhere it can be delivered to the workplace quickly. Electronic copies are fine, as long as the crew can actually open them on site.
How is Victoria different?
Victoria runs its own Occupational Health and Safety Act 2004 and OHS Regulations 2017. According to WorkSafe Victoria:
- Victoria lists 19 types of high risk construction work, not 18.
- The duty holder, in consultation with affected employees and their health and safety representative, must review and if necessary revise the SWMS whenever the HRCW changes, if there is a sign the controls are not working, or after any incident during the HRCW.
- A copy must be kept for the duration of the HRCW, and copies can be kept electronically.
- Hand-written amendments can be made on site.
See SWMS requirements by state for the Act and regulator in each state.
Starting from a template
A template gives you the structure, the hazards and controls for the trade, and sign-on and review sections. You still have to add the site, the crew and the controls for this job before you use it. See how to use a SWMS template.
Our trade packs are $249.99 per state, editable Word, one-off purchase. For example:
- Plumbing: 24 SWMS
- Electrical Combined HVAC and Solar: 40 SWMS
- Civil Works: 49 SWMS
Or browse all trade packs. To check whether your work needs a SWMS at all, see do I need a SWMS? and high risk construction work.
Common questions
How long do you have to keep a SWMS?
Under the model WHS Regulations, until the high risk construction work it covers is finished. If a notifiable incident happens in connection with that work, keep it for at least 2 years after the incident. In Victoria, keep a copy for the duration of the high risk construction work. Electronic copies are fine.
Does a SWMS have to be signed?
The model WHS Regulations do not say the SWMS must be signed. The Construction Code says a SWMS may include the names and signatures of the workers consulted, and most principal contractors require a sign-on as a site rule. Signatures are good evidence that the crew was consulted and briefed.
When must a SWMS be reviewed?
Under the model WHS Regulations, review it and revise it as necessary whenever the relevant control measures are revised. In Victoria, review it whenever the high risk construction work changes, if there is a sign the controls are not working, or after any incident during the work.
Do I give my SWMS to the principal contractor?
On a construction project under the model WHS Regulations, yes: a copy must be given to the principal contractor before the high risk construction work starts. Victoria words the principal contractor’s role differently, so check WorkSafe Victoria.
What happens if the work does not match the SWMS?
Stop the work immediately, or as soon as it is safe to, and do not start again until it can be done in line with the SWMS. If the SWMS method is wrong for the job, review and revise it before restarting.
Sources: Model WHS Regulations, regulations 299–303, Model Code of Practice: Construction work, Safe Work Australia SWMS information sheet and WorkSafe Victoria—SWMS. Model provisions are adopted by each jurisdiction in its own laws; check yours.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.