You need a Safe Work Method Statement (SWMS) when the job is construction work and it falls into one of the 18 high risk categories, such as a fall of more than 2 metres, a trench deeper than 1.5 metres or working where mobile plant moves. The size of the job and the size of your business do not change that. Clients and principal contractors can also ask for one when the law does not.
The three questions
- Is it construction work? If not, the SWMS rules do not apply.
- Does it fall into a high risk category? If yes, a SWMS is required before the work starts.
- Does the site or contract ask for one anyway? If yes, it is a condition of getting on site, even if the law does not require it.
1. Is it construction work?
Under the model WHS Regulations, construction work is any work connected with building, altering, converting, fitting out, commissioning, renovating, repairing, maintaining, refurbishing, demolishing, decommissioning or dismantling a structure. It also covers:
- installing or testing as part of that work
- excavation, site preparation and landscaping as part of site preparation
- installing, testing or maintaining essential services in a structure
- assembling prefabricated elements, and removing demolition waste.
“Structure” is wide too: roads, paths, earthworks, bridges, dams, sewers and drainage all count, as well as buildings.
Some work is not construction work. The main one for trades is testing, maintenance or repair work of a minor nature. The model Code of Practice: Construction work gives examples under that heading, but only where the work really is minor:
- regular inspections of a building’s fire equipment or lifts
- servicing or repairing an air conditioning system
- replacing or repairing solar panels
- replacing or repairing a damaged door, or individual roof tiles
- repainting a wall in an existing home
- replacing or repairing carpet in a house not under construction.
The Code says work is of a minor nature only if it needs little or no pre-start preparation, is small scale and needs minimal control measures: for example, hand tools, no change to the building’s design or stability, and roads and footpaths unaffected. The same Code lists installing solar panels as construction work. So the examples are not blanket exemptions. A big air conditioning repair, or solar work that needs edge protection on a two-storey roof, may well be construction work, and high risk construction work if there is a risk of falling more than 2 metres or work near energised electrical installations.
Making building elements such as trusses or windows in a factory that supplies the industry is not construction work either, and nor is building a transportable home that will be moved elsewhere. Making them at the construction site is.
Be careful with “minor”. Fixing defects during the defects liability period is construction work. So is anything that turns into a bigger job once you open it up.
2. Is it high risk construction work?
The model Regulations list 18 categories. Construction work is high risk if it:
- involves a risk of a person falling more than 2 metres
- is on a telecommunication tower
- involves demolishing a load-bearing or structural element
- involves, or is likely to involve, disturbing asbestos
- involves structural alterations or repairs needing temporary support
- is in or near a confined space
- is in or near a shaft or trench deeper than 1.5 metres, or a tunnel
- involves explosives
- is on or near pressurised gas mains, or chemical, fuel or refrigerant lines
- is on or near energised electrical installations or services
- is in an area that may have a contaminated or flammable atmosphere
- involves tilt-up or precast concrete
- is on, in or next to a road, railway, shipping lane or other traffic corridor in use
- is in an area where powered mobile plant moves
- is in an area with artificial extremes of temperature
- is in or near water or other liquid with a risk of drowning
- involves diving work.
One category is enough. Most real jobs hit several, and one SWMS can cover all of them. What each category means in practice, with examples, is in our guide to the 18 categories of high risk construction work.
Worked examples
- Replacing a few cracked roof tiles on a single-storey house: the Code lists replacing individual roof tiles as an example of minor repair work. If it really is small, with hand tools and little preparation, it is not construction work. You still have to manage the fall risk, and many clients will still want a SWMS.
- Re-roofing the same house: construction work, with a risk of falling more than 2 metres. SWMS required.
- Routine service of a split system: the Code gives servicing an air conditioning system as an example of minor work, but only where it is minor in scale and preparation. A repair that needs the unit lifted off a roof, or work near live electrical parts, is a different job. Installing a new system with the outdoor unit on the roof is construction work, and usually high risk because of the fall height and the refrigerant lines.
- Digging a 1.2 m trench with a mini excavator: the trench is under 1.5 m, but powered mobile plant is moving in the area, so it is still high risk construction work.
- Cutting into an asbestos cement sheet wall during a renovation: the Code’s own example of work involving asbestos. SWMS required, and the removal rules apply too.
For specific trades, see earthmoving and plant tasks, electrical and HVAC tasks, asbestos removal and confined spaces.
3. Does the site ask for one anyway?
Many principal contractors, builders and government clients ask for a SWMS for every trade on site, high risk or not, as part of prequalification or the site induction. That is a contract or site rule rather than the regulation, but if you want the job, it is just as real.
For work outside the high risk categories, a Job Safety Analysis (JSA) or a risk assessment is often accepted instead. Ask what the site wants before you turn up. See SWMS vs JSA.
Who has to prepare it?
The person conducting a business or undertaking (PCBU) that carries out the high risk work, before the work starts. For most jobs, that means the contractor or subcontractor doing the work, prepared with the workers who will do it.
- Sole traders are PCBUs too. The Code says self-employed people are also workers for their own business, so they carry both sets of duties.
- Subcontractors prepare their own SWMS. On a construction project the principal contractor must get a copy before the work starts. See the subcontractor safety paperwork checklist.
- Owner-builders may have PCBU duties. See the owner-builder guide.
- A homeowner who just hires a tradie to work on their home is not the one who prepares the SWMS.
What if you are not sure?
If you cannot rule a category out, treat the work as high risk and prepare a SWMS. A SWMS for work that turns out not to need one costs you an hour. Missing one that was needed can stop the job, and it leaves the crew without a plan for the dangerous part. Your regulator can also answer the question for a specific job.
Is it different in each state?
Every state and territory except Victoria has adopted the model WHS laws, so the test above applies with small local differences. Victoria requires a SWMS under its own OHS Regulations 2017, where the duty applies if there is a risk to anyone’s health or safety from the work. Its construction work definition leaves out “routine or minor” testing, maintenance or repair work, which is worded differently from the model. It lists 19 types of high risk construction work, for example any demolition rather than only load-bearing elements, and tunnels as their own type. See SWMS requirements by state.
How do you get a SWMS?
Write your own (see how to write a SWMS) or start from a template and tailor it to the site (see how to use a SWMS template). Our trade packs have every SWMS for the trade, written for your state, in editable Word, plus the SOP pack, for $249.99 per state. Not sure which? See which SWMS pack do I need?
Common questions
When is a SWMS legally required?
Under the model Work Health and Safety (WHS) Regulations, a Safe Work Method Statement (SWMS) must be prepared before high risk construction work starts. Work is high risk construction work if it is construction work and falls into one of the 18 categories, such as a risk of falling more than 2 metres, a trench deeper than 1.5 metres or powered mobile plant.
Do I need a SWMS for a small job?
The size of the job is not the test. If it is construction work in one of the high risk categories, you need a SWMS, even for a few hours’ work. Testing, maintenance or repair work of a minor nature is not construction work, but only if it is genuinely minor: little or no preparation, small scale, and minimal controls. If you are not sure, treat it as construction work.
I am a sole trader. Do I still need a SWMS?
Yes, if you do high risk construction work. A self-employed person is a person conducting a business or undertaking (PCBU), and the SWMS duty applies to the PCBU that carries out the work, whatever its size.
Do I need a SWMS if the work is not high risk?
Not by law under the model regulations. You still have to manage the risks so far as is reasonably practicable. A client or principal contractor can also require a SWMS, or a Job Safety Analysis (JSA), as a contract or site rule.
Is it different in Victoria?
The idea is the same, but Victoria uses its own OHS Regulations 2017 and lists 19 types of high risk construction work. For example, it lists demolition and tunnels as separate types. Check WorkSafe Victoria’s list for work in Victoria.
Sources: Model WHS Regulations (regulations 289, 291 and 299), Model Code of Practice: Construction work (sections 2 and 4, Tables 1–3) and WorkSafe Victoria—SWMS. General information only; if you are not sure whether your work is high risk construction work, ask your regulator.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.