Under the model WHS Regulations, a construction project is construction work costing $250,000 or more. It must have one principal contractor, who prepares a WHS management plan before work starts and takes reasonable steps to get a Safe Work Method Statement (SWMS) for all high risk construction work (HRCW) before that work starts. The test is not the same everywhere: South Australia uses $450,000 or more, Victoria $350,000 or more, the Northern Territory $1,000,000 or more from 28 May 2026 ($500,000 or more if work on the project began before then), and Western Australia counts people on site, not dollars.
Always confirm the current figure with your regulator before relying on it, including the figures on this page.
What is a construction project?
The model WHS Regulations define a construction project as a project involving construction work where the cost of the construction work is $250,000 or more. The model Code of Practice: Construction work says it covers the work up to handover to the person who commissioned it, usually at practical completion.
Below the threshold, there is no legal principal contractor role and no WHS management plan is required by these rules. But the SWMS rules still apply to any high risk construction work, and every business still has its general health and safety duties. See do I need a SWMS?
Who is the principal contractor?
Under the model WHS Regulations, the person conducting a business or undertaking (PCBU) that commissions the construction project is the principal contractor, unless it engages another PCBU as principal contractor and authorises it to have management or control of the workplace. There can only be one principal contractor for a project at a time. For who counts as a PCBU, see what is a PCBU?
Homeowners are treated differently. If you are building or renovating your own home, see owner-builders: who provides the SWMS?
What must the principal contractor do?
The Construction Code sets out the principal contractor’s duties under the model WHS Regulations. They include:
- Signs clearly visible from outside the workplace, showing the principal contractor’s name, phone numbers including an after-hours number, and the site office location if there is one.
- A WHS management plan, in writing, before work on the project starts.
- Telling people about the plan, so far as is reasonably practicable, so everyone who works on the project knows its content and their right to inspect it.
- Reviewing the plan to keep it up to date, and telling people about the changes.
- Getting the SWMS: taking all reasonable steps to get a copy of the SWMS for high risk construction work before that work starts.
- Managing site-wide risks, including materials and waste, plant not in use, traffic near the workplace and essential services.
- Keeping the plan until the project is completed, or for at least 2 years after a notifiable incident.
For checking the SWMS you collect, see how to review a subcontractor’s SWMS.
What goes in the WHS management plan?
Under the model WHS Regulations, the plan must include:
- the names, positions and health and safety responsibilities of people with specific safety roles, such as site supervisors, project managers and first aid officers
- the arrangements for consultation, cooperation and coordination between the businesses on site
- the arrangements for managing incidents
- the site-specific health and safety rules, and how people will be told about them
- the arrangements to collect, assess, monitor and review SWMS.
The Code says it may also cover things such as the hazardous chemicals register, plant, traffic management, essential services, site security and psychosocial hazards.
A WHS management plan is for one project. It is not the same as a WHS management system, which covers how a business manages safety across all its work. See what is a WHS management system?
How does each state compare?
Each state and territory sets its own test in its own regulations, usually regulation 292. These are the tests as written in each state’s regulations on 10 November 2026. Where a regulator says GST is excluded from the cost, the table says so; elsewhere, check with the regulator.
| Where | When it is a construction project | Project plan |
|---|---|---|
| Model WHS Regulations | Construction work costing $250,000 or more | WHS management plan |
| New South Wales | Construction work valued at $250,000 or more | WHS management plan |
| Australian Capital Territory | Construction work costing $250,000 or more | WHS management plan |
| South Australia | Construction work costing $450,000 or more (SafeWork SA: excluding GST) | WHS management plan |
| Western Australia | 5 or more persons are, or are likely to be, working at the same time at a construction site | WHS management plan |
| Victoria | Construction project costing $350,000 or more ($250,000 or more if the contract was entered into before 1 July 2014) | Health and safety coordination plan |
| Queensland | Construction work costing $250,000 or more (Workplace Health and Safety Queensland: excluding GST) | WHS management plan |
| Tasmania | Construction work costing $250,000 or more | WHS management plan |
| Northern Territory | Construction work costing $1,000,000 or more from 28 May 2026 ($500,000 or more if work on the project began before then) | WHS management plan |
Victoria runs its own Occupational Health and Safety Act 2004 and OHS Regulations 2017. Under regulation 332, the principal contractor and health and safety coordination plan duties apply to a construction project costing $350,000 or more, so a job at exactly $350,000 is included. The cost is valued the way the Building and Construction Industry Security of Payment Act 2002 values construction work. For construction contracts entered into before 1 July 2014, the old $250,000 threshold still applies. WorkSafe Victoria’s pocket guide to construction safety explains the coordination plan. The duties are similar in purpose to the model rules but worded differently, so read WorkSafe Victoria’s guidance for work there.
Western Australia has adopted the WHS laws but has no dollar threshold. A construction project is one where 5 or more persons are, or are likely to be, working at the same time at a construction site.
The Northern Territory raised its threshold to $1,000,000 from 28 May 2026. The old $500,000 threshold still applies to a project if work on it began before that date.
For the Act and regulator in each state, see SWMS requirements by state.
What does this mean for subcontractors?
On a construction project, a business doing high risk construction work must give the principal contractor a copy of its SWMS before that work starts, and the SWMS must take the WHS management plan into account. See keeping, signing and reviewing a SWMS and the subcontractor safety paperwork checklist. Councils and government clients often ask for more at tender. See council and government tender prequalification.
Templates for the job
For the SWMS on civil and infrastructure jobs, the Civil Works trade pack includes 49 SWMS. It is $249.99 per state, editable Word, one-off purchase. For other trades, browse trade packs or see which SWMS pack do I need?
Principal contractors who also need the policies, procedures, registers and forms behind a WHS management plan can look at the All-In WHS Packs. A template gives you the structure. It still has to be completed for the project, and it does not make anyone compliant on its own.
Common questions
When does a job need a principal contractor?
When it is a construction project. Under the model WHS Regulations that is construction work costing $250,000 or more, but the test differs between states: South Australia uses $450,000 or more, Victoria $350,000 or more, the Northern Territory $1,000,000 or more from 28 May 2026 ($500,000 or more if work on the project began before then), and Western Australia a headcount of 5 or more people working at the same time. Confirm the current test with your regulator.
Who is the principal contractor?
The person conducting a business or undertaking (PCBU) that commissions the construction project, unless it engages another PCBU as principal contractor and authorises it to have management or control of the workplace. There can only be one principal contractor for a project at a time.
What must be in a WHS management plan?
Under the model WHS Regulations: the people with specific health and safety responsibilities, the arrangements for consultation, cooperation and coordination, how incidents will be managed, the site safety rules and how people are told about them, and the arrangements to collect, assess, monitor and review Safe Work Method Statements (SWMS).
Is a WHS management plan the same as a WHS management system?
No. The plan is for one construction project and is prepared by the principal contractor before work starts. A WHS management system is how a business manages health and safety across all its work.
Does a smaller job still need a SWMS?
Yes, if the work is high risk construction work. The construction project threshold decides whether there must be a principal contractor and a WHS management plan. It does not decide whether a SWMS is needed.
Sources: Model WHS Regulations, regulations 292 and 293, Model Code of Practice: Construction work, SafeWork NSW, WorkSafe ACT, SafeWork SA, WHS (General) Regulations 2022 (WA), WHS Regulation 2011 (Qld) and Workplace Health and Safety Queensland, WHS Regulations 2022 (Tas), WHS (National Uniform Legislation) Regulations 2011 (NT) and OHS Regulations 2017 (Vic), regulations 332 and 558. Thresholds change; confirm the current test with your regulator before relying on it.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.