High risk construction work: the 18 categories, with examples

Last reviewed:

If construction work falls into any of the 18 categories of high risk construction work (HRCW) in the model Work Health and Safety (WHS) Regulations, a Safe Work Method Statement (SWMS) must be prepared before it starts. Here is each category in the regulation’s own words, with the examples Safe Work Australia gives for it.

The categories only apply to construction work. Some minor testing, maintenance and repair work is not construction work at all. Check that first in do I need a SWMS?

The 18 categories

Under regulation 291 of the model WHS Regulations, construction work is high risk if it involves or is carried out in the following. Examples are from Appendix C of the model Code of Practice: Construction work.

The 18 categories of high risk construction work with examples
#CategoryExamples
1A risk of a person falling more than 2 metresInstalling roof trusses, tiles or sheeting; putting an evaporative cooler on a house roof; working next to a pit or opening with more than a 2 m drop.
2Work on a telecommunication towerInstalling equipment on a telecommunications tower.
3Demolition of an element that is load-bearing or related to the structure’s physical integrityKnocking out a load-bearing wall in a house; removing wall or roof bracing in a renovation.
4Work that involves, or is likely to involve, disturbing asbestosLifting floor tiles containing asbestos; cutting or drilling into an asbestos cement sheet wall; working on asbestos cement pipe.
5Structural alterations or repairs that need temporary support to prevent collapsePropping a ceiling while a load-bearing wall is removed.
6Work in or near a confined spaceConnecting a new sewer to a main in a 3 m trench; unblocking a sewer from inside a large underground pit.
7Work in or near a shaft or trench deeper than 1.5 metres, or a tunnelLaying or testing pipes in a trench over 1.5 m deep; working near bored piers over 1.5 m deep.
8Use of explosivesBlasting rock or a tree stump. Explosive-powered tools do not count.
9Work on or near pressurised gas distribution mains or pipingExcavating foundations near an existing gas supply.
10Work on or near chemical, fuel or refrigerant linesDigging or drilling where you could hit or puncture a fuel, chemical or refrigerant line.
11Work on or near energised electrical installations or servicesDrilling into a wall where live wiring may be; working near overhead or underground power lines.
12Work in an area that may have a contaminated or flammable atmosphereRemoving pipework or tanks that may hold chemical residue; demolishing a petrol station; decommissioning plant.
13Tilt-up or precast concreteBuilding units from precast panels; installing a precast drainage pit.
14Work on, in or next to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestriansUsing part of the road to deliver materials; digging up kerb and gutter for drainage; building an extra lane.
15Work in an area where there is any movement of powered mobile plantWorking in part of a site not separated from skid steers, backhoes, mobile cranes or trucks.
16Work in an area with artificial extremes of temperatureInside enclosed roof cavities; in an operating cool room or freezer; next to an operating boiler.
17Work in or near water or other liquid with a risk of drowningShade sails or a gazebo beside a pool; building a bridge over a river; restoring a wharf.
18Diving workDivers doing structural repairs to a jetty, marina, wharf or pier.

Reading the categories

Most jobs hit more than one

WorkSafe Victoria gives a good example: installing sewer pipes in a 4 metre deep trench, next to a freeway, under overhead power lines, with an excavator. That is a fall of more than 2 metres, a trench over 1.5 metres, energised services, a traffic corridor and powered mobile plant, all in one job.

One SWMS can cover every category in the job, or you can prepare one for each. What matters is that every high risk part is covered. WorkSafe Victoria points out that other hazards on the job, such as falling objects, still have to be managed, but do not have to be in the SWMS.

Which trades hit which categories?

Trade-by-trade detail: earthmoving and plant, electrical and HVAC, asbestos removal and confined spaces.

How is Victoria’s list different?

Victoria lists 19 types of high risk construction work under its OHS Regulations 2017. Most match the model list, but a few are worded differently:

In Victoria, use WorkSafe Victoria’s list. See SWMS requirements by state.

What next?

If your work is in one or more categories, the SWMS has to identify that work, its hazards and risks, the controls and how they will be checked, before the work starts. See how to write a SWMS, or work out the hazards first with a risk assessment and our free Risk Assessment Builder.

Our trade packs cover the high risk tasks for each trade, written for your state, in editable Word, plus the SOP pack. Each is $249.99 per state. See which SWMS pack do I need?

Common questions

How many categories of high risk construction work are there?

The model Work Health and Safety (WHS) Regulations list 18. Victoria lists 19 types under its own OHS Regulations 2017. If construction work falls into any one category, a Safe Work Method Statement (SWMS) must be prepared before it starts.

What does “near” mean?

The Construction Code says “near” means close enough that there is a risk of hitting or puncturing the gas main, pipe, line, electrical installation or service. It is about the risk, not a fixed distance.

Is using power tools “near energised electrical installations”?

No. The Construction Code says electrical installations and services do not include appliances such as power leads and electrically powered tools. Drilling into a wall that may have live wiring in it is a different matter: that is one of the Code’s examples of the category.

Does high risk construction work always need a SWMS?

Under the model regulations, yes. The PCBU carrying out the work must make sure a SWMS is prepared before it starts, whatever the size of the job. The work must be construction work in the first place; some minor testing, maintenance and repair work is not.

Can one SWMS cover several categories?

Yes. A trench next to a road with an excavator working hits three categories, and one SWMS can cover all of them, as long as it covers every high risk part of the job. You can also prepare separate SWMS, but check the controls do not conflict.

Sources: Model WHS Regulations (regulations 289 and 291), Model Code of Practice: Construction work (Appendix C) and WorkSafe Victoria—SWMS. General information only; whether a category applies depends on the job, so check with your regulator if unsure.

Start from a proper SWMS, not a blank page

State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.

This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.