You need a Safe Work Method Statement (SWMS) when the job is high risk construction work (HRCW). For electrical, air conditioning and solar work, the usual triggers are work on or near energised electrical installations or services, falls over 2 metres, refrigerant lines, powered mobile plant such as EWPs, and trenches deeper than 1.5 metres.
This page is for electrical, HVAC and solar businesses. For the general test, see do I need a SWMS? To compare all the packs, see which SWMS pack do I need?
Which categories matter for electrical and HVAC work?
The model WHS Regulations list 18 categories of HRCW. The full list is in our high risk construction work guide. The ones electrical and HVAC crews hit most are construction work that:
- is carried out on or near energised electrical installations or services
- involves a risk of a person falling more than 2 metres
- is carried out on or near chemical, fuel or refrigerant lines
- is carried out in an area with movement of powered mobile plant
- is carried out in or near a shaft or trench deeper than 1.5 metres
- is carried out in or near a confined space
- is carried out in an area with artificial extremes of temperature, such as cool rooms and freezers.
Older buildings can add a further category: construction work that involves, or is likely to involve, disturbing asbestos. See asbestos removal SWMS and licences.
A note on “energised”
The category is about work on or near energised installations or services. Isolation, lock-out and testing for dead are the core controls, and the SWMS should say how they are done. But isolating one circuit does not always take the whole job out of the category. Other circuits, other trades, solar and battery back-feeds, and overhead or underground services can leave live parts near the work. If in doubt, treat it as HRCW.
Common jobs and the categories they often trigger
This is a guide, not a ruling. Whether a category applies depends on the site and the job.
| Task | Often triggers | Note |
|---|---|---|
| New installations, switchboards and renovations in existing buildings | Work on or near energised electrical installations or services | Existing circuits, other trades and back-feeds can leave live parts near the work. |
| Rooftop solar installation | Falls over 2 m; energised installations, including DC from the panels | Roof edges, brittle roofing and skylights are the usual fall points. |
| Ground-mounted solar farms | Powered mobile plant; energised installations; trenches over 1.5 m where dug | Pile driving and cable trenching bring plant and excavation in. |
| Air conditioning installation (split and ducted) | Falls over 2 m for outdoor units on walls or roofs; refrigerant lines; energised installations | Roof space work can also bring heat and asbestos in older buildings. |
| Refrigerant recovery, charging and brazing | Work on or near refrigerant lines | Licensing for refrigerant handling is separate from the SWMS. |
| Cool rooms and refrigeration plant | Artificial extremes of temperature; refrigerant lines | Entrapment and low oxygen from leaks are also hazards. |
| EWP and work at height on structure | Falls over 2 m; powered mobile plant | Overhead power lines add the energised services category. |
| Trenching for cables and conduit | Trench deeper than 1.5 m; powered mobile plant; buried services | Locate services before digging. |
| Risers, pits and ceiling voids | Possibly a confined space; falls through openings | Whether a space is confined depends on its features, not its name. |
| Working near overhead power lines | Work near energised electrical installations or services | Approach distances come from your regulator and the network operator. |
The model WHS Regulations say construction work does not include “testing, maintenance or repair work of a minor nature carried out in connection with a structure.” The model Construction Work Code of Practice gives examples under that heading, including servicing or repair of an air-conditioning system, and replacing or repairing solar panels, but only where the work is of a minor nature: little or no pre-start preparation, small scale, and minimal control measures (for example, hand tools and no change to the building’s design or stability). Installing solar panels is listed in the same Code as construction work.
If the job is not minor, or if it is construction work that is also high risk construction work (such as work with a risk of a person falling more than 2 metres, or work on or near energised electrical installations), a SWMS is required before that work starts. A principal contractor or client may still ask for a SWMS even when the legal trigger isn’t met. Check the Code and regulator adopted in the state or territory where the work is done. Victoria uses its own wording, “routine or minor testing, maintenance or repair work”, so do not treat it as identical.
A client or principal contractor can also ask for a SWMS for work outside these categories, as a contract or site rule. That is their requirement, not the regulation’s.
For confined spaces such as risers and pits, the SWMS sits beside an entry permit, a standby person and a rescue plan. See confined space entry and rescue. A competent person has to complete the entry permit.
Refrigerants, chemicals and licences
Refrigerant work can involve flammable refrigerants, pressurised systems, brazing and gas displacing oxygen in enclosed rooms. The SWMS should cover the method and controls. It sits beside the safety data sheet (SDS) for the refrigerant and any licence or permit needed to handle it. Check the licensing and accreditation requirements for refrigerant handling, electrical work and solar installation with the relevant authority. A SWMS does not replace any of them.
Which pack fits?
All three are $249.99 per state, editable Word, one-off purchase.
- Electrical Combined HVAC and Solar (40 SWMS) covers the lot: New Electrical Installation, Switchboard Installation, Solar Installation (Roof), Ground-Based Solar Farm Installation, Air Conditioning Installation, Refrigerant Gas Handling, Refrigeration & Cool Rooms, Excavation & Trenching, EWP Operations, Working at Heights, Working Near Overhead Power Lines, Confined Space Work, Risers, Working in Roof Spaces, Lock Out Tag Out and EV Charger Installation.
- Electrical Work General (30 SWMS) suits electricians who do not take on air conditioning, refrigeration or solar.
- Electrical Air Conditioning and Refrigeration (HVAC) (23 SWMS) suits businesses that mainly install and service air conditioning and refrigeration.
Compare the task lists with the jobs you take on. If your work spans electrical, HVAC and solar, the combined pack usually saves buying two.
What still has to be tailored?
Before the SWMS goes to site, add the site, the installation, your isolation and testing method, access equipment, the crew’s licences and competencies, and who supervises. See how to use a SWMS template, and keeping, signing and reviewing a SWMS for when it must be updated.
Victoria and other states
Victoria lists 19 types of HRCW under its own OHS Regulations 2017. They are similar to the model list but worded separately. Other states and territories have adopted the model list in their own regulations. See SWMS requirements by state.
Common questions
Does all electrical work need a SWMS?
No. A Safe Work Method Statement (SWMS) is required for high risk construction work. Construction work on or near energised electrical installations or services is one of the categories, and electrical jobs often add others, such as falls over 2 metres or trenches deeper than 1.5 metres. Work that is not construction work, or not high risk construction work, may not need one by law, though a client can still ask for it.
If I isolate the circuit, do I still need a SWMS?
Isolating and testing for dead is a core control, but it does not always take the job out of the category. Other circuits, other trades, solar and battery back-feeds and overhead services can leave energised parts near the work. If you are unsure, treat it as high risk construction work and check with your regulator.
Which pack covers solar and air conditioning together?
The Electrical Combined HVAC and Solar pack covers electrical installation, air conditioning, refrigeration and solar work in one pack. If you only do general electrical work, or only air conditioning and refrigeration, the smaller packs may fit better.
Does a SWMS replace my electrical or refrigerant licence?
No. Licences, accreditations and competencies are separate requirements. The SWMS records how the job will be done safely; it does not authorise anyone to do licensed work.
Sources: Model WHS Regulations, regulation 291, Model Code of Practice: Construction work and WorkSafe Victoria—SWMS. General information only; whether a category applies depends on the job, so check with your regulator if unsure.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.