You need a Safe Work Method Statement (SWMS) for concreting work that is high risk construction work (HRCW). For concreters, the categories that come up most are tilt-up or precast concrete, areas where powered mobile plant such as concrete trucks and pumps is moving, falls of more than 2 metres from formwork decks and edges, trenches deeper than 1.5 metres for footings, and structural work that needs temporary support.
Cutting, grinding and coring concrete is not itself a category, but it can bring in the crystalline silica rules, which sit beside the SWMS. This guide matches common concreting tasks to the categories, then covers what the SWMS must say and what else the job may need.
For the general test, see do I need a SWMS?. For the full list, see high risk construction work: the 18 categories.
When is concreting construction work?
Concreting is construction work when it is carried out in connection with the construction, alteration, renovation, repair, maintenance or refurbishment of a structure, including the prefabrication of elements at a place specifically established for the construction work (regulation 289 of the model Work Health and Safety (WHS) Regulations; section 289 of Queensland's WHS Regulation 2011). Minor testing, maintenance or repair work on a structure is excluded (r 289(3)(d)).
Which high risk construction work categories matter for concreting?
The model WHS Regulations list 18 categories in regulation 291 (section 291 in Queensland). The ones concreters hit most are construction work that:
- involves tilt-up or precast concrete
- is carried out in an area at a workplace in which there is any movement of powered mobile plant
- involves a risk of a person falling more than 2 metres
- is carried out in or near a shaft or trench with an excavated depth greater than 1.5 metres
- involves structural alterations or repairs that require temporary support to prevent collapse
- involves demolition of an element of a structure that is load-bearing or otherwise related to the physical integrity of the structure
- is carried out on or near energised electrical installations or services
- is carried out in or near a confined space.
Common concreting jobs and the categories they often trigger
This is a guide, not a ruling. The structure, the height, the plant and the excavations decide which categories apply.
| Concreting task | Often triggers | Note |
|---|---|---|
| Tilt-up panel casting, lifting and propping | Tilt-up or precast concrete; powered mobile plant | Lifting, bracing and the exclusion zone belong in the method. |
| Precast panel installation | Tilt-up or precast concrete; falls over 2 m; powered mobile plant | Crane, rigging and temporary bracing details. |
| Suspended slabs and formwork decks | Falls over 2 m; powered mobile plant | Edge protection and the formwork's design and inspection. |
| Concrete pumping (boom or line) | Powered mobile plant; possibly energised overhead lines | A concrete placing boom needs a high risk work licence; a line pump without a placing boom is not in that licence class. |
| Footings, piers and pad excavations | Trench or shaft over 1.5 m; powered mobile plant | Support for the excavation, not just the pour. |
| Slab on ground with trucks on site | Powered mobile plant | Truck movements, reversing and the washout area. |
| Underpinning and propping existing structures | Temporary support; trench over 1.5 m | Engineer's sequence and propping. |
| Saw cutting, coring and chasing structural concrete | Possibly load-bearing demolition; energised electrical services | Scan for services and get engineering sign-off where structural. |
| Small paths and driveways with no plant | Often none | A builder can still ask for a SWMS as a site rule. |
What must a concreting SWMS cover?
Regulation 299 of the model WHS Regulations (section 299 in Queensland) says a SWMS must:
- identify the work that is high risk construction work
- state the hazards relating to that work and the risks to health and safety associated with those hazards
- describe the measures to be implemented to control the risks
- describe how the control measures are to be implemented, monitored and reviewed.
It must take into account the circumstances at the workplace and, on a construction project, the principal contractor's WHS management plan, and be readily accessible and understandable to the people who use it.
For concreting, that usually means the SWMS sets out:
- for tilt-up and precast: the lifting design, inserts, crane and rigging, bracing, and the exclusion zone during lifts
- the formwork and edge protection, and who confirms the formwork is ready to take the pour
- how trucks, pumps and other plant are separated from the crew, including reversing and washout areas
- the pump set-up, the boom's position relative to overhead power lines, and the operator's licence
- excavation depth and support for footings and piers
- how cutting, coring and grinding dust is controlled, such as water suppression or on-tool extraction, and the respiratory protective equipment (RPE) used
- how wet cement burns are prevented
- who supervises, and how the controls will be checked.
Workplace Health and Safety Queensland (WHSQ) says statements such as "use appropriate PPE" (personal protective equipment) do not detail the control measures. Name the control you will use.
What sits beside the concreting SWMS?
Silica. Safe Work Australia's crystalline silica code of practice gives examples of silica-generating work including brick, concrete or stone cutting, and angle grinding or jack hammering of concrete or masonry. Under the model WHS Regulations, a person conducting a business or undertaking (PCBU) processing a crystalline silica substance in a way that is high risk must ensure a silica risk control plan is prepared before the processing starts (regulation 529CB; section 529CB in Queensland). A separate plan is not needed if the processing is also high risk construction work and the SWMS, prepared before the processing starts, meets the plan's content requirements. See what is a silica risk control plan?.
Exposure limits. From 1 December 2026, workplace exposure limits (WEL) replace the workplace exposure standards (WES). Safe Work Australia says PCBUs must comply with the WES list up to and including 30 November 2026, and with the WEL list from 1 December 2026. Victoria has made its own amendment regulations, which also commence on 1 December 2026, and some jurisdictions have transition arrangements for particular substances, so check your regulator before quoting a limit for cement or silica dust. See what are WES and WEL?.
Licences. Operating a concrete placing boom is a class of high risk work that needs a high risk work licence (regulation 81 and schedule 3 of the model WHS Regulations; the same in Queensland). Crane and dogging or rigging work for tilt-up and precast lifts has its own licence classes.
Plant procedures. Concrete saws, core drills, grinders, vibrators and power trowels are better covered by safe operating procedures (SOPs) beside the SWMS.
What is in the Concreting pack?
The Concreting SWMS Trade Pack has 34 SWMS: one Concreting Master SWMS and 33 task SWMS. They include:
- Steel Fixing
- Formwork - Decks, Columns & Stairs
- Concrete Foundations - Excavating & Pouring
- Concrete Slab on Ground
- Concrete Waffle Pod Raft System
- Concrete Piling
- Concrete Underpinning
- Concrete Pumping (Boom - Line)
- Concrete Placement & Finishing
- Pre-cast - Tilt-up Panels
- Tilt-up Panel Lifting
- Concrete Sawing & Core Drilling
- Concrete Scanning
- Concrete Grinding & Polishing
- Trench Excavation
- Silica Dust
- Heat Stress
The full list also covers site establishment, deliveries, shotcrete, kerb and channel, grout pumps, mobile batching, crushing, chasing, sealing, patching, washout and work in private residences. The pack comes in editable Word with a free pack of 27 safe operating procedures (SOPs). Each state edition references that state's Act and regulator.
What still has to be tailored?
Before the SWMS goes to site, add:
- the site, the builder and the date
- the panel or pour details, the lifting design and the engineer's requirements
- the formwork system, who designed it and who confirms it is ready
- the plant on site, the operators and their licences
- the services scanned or located before cutting or coring
- the dust controls and RPE you will use
- who supervises, and the crew's sign-on after you have talked it through with them.
See how to use a SWMS template and keeping, signing and reviewing a SWMS.
Victoria and other states
Victoria uses the Occupational Health and Safety (OHS) Regulations 2017, made under the OHS Act 2004. Its 19 types of high risk construction work include work "involving tilt-up or precast concrete" (regulation 322). For silica, Victoria does not use the model silica risk control plan. An employer or self-employed person must not perform high risk crystalline silica work unless a crystalline silica hazard control statement is prepared before the work starts and the work is done in line with it (regulation 319L, in Part 4.5).
The other states and territories have adopted the model WHS Regulations in their own laws, and most use the same silica risk control plan rule. See SWMS requirements by state.
Common questions
Does concreting need a SWMS?
Concreting needs a Safe Work Method Statement (SWMS) when the work is high risk construction work, such as tilt-up or precast concrete, work where concrete trucks and pumps are moving, pours on formwork decks where a person could fall more than 2 metres, or footings in trenches deeper than 1.5 metres. Small jobs with no plant may fall outside the categories.
Is tilt-up concrete high risk construction work?
Yes. Construction work that involves tilt-up or precast concrete is one of the high risk construction work categories under the model WHS Regulations, and Victoria lists it too. The SWMS should cover the lifting, bracing and exclusion zones, not only the pour.
Is concrete cutting covered by the SWMS?
Cutting, coring and grinding concrete is not itself a high risk construction work category, but the dust controls belong in the SWMS when the task is part of high risk construction work. Where processing a crystalline silica substance is high risk, the model WHS Regulations also require a silica risk control plan, unless the SWMS meets the plan's requirements.
Do I need a licence to operate a concrete pump?
Operating a concrete placing boom is a class of high risk work that needs a high risk work licence under the model WHS Regulations. Line pumps without a placing boom are not in that licence class, but the operator still needs training and the pump needs to be managed as plant.
Is the list different in Victoria?
Victoria uses its own OHS Regulations 2017 and lists 19 types of high risk construction work, including tilt-up or precast concrete. For silica, Victoria uses a crystalline silica hazard control statement instead of a silica risk control plan.
Sources: Work Health and Safety Regulation 2011 (Qld), sections 81, 289, 291, 299 and 529CB, and schedule 3 (concrete placing boom), Model WHS Regulations numbering, Occupational Health and Safety Regulations 2017 (Vic), Authorised Version No. 018 (as at 20 October 2026), regulations 319C, 319D, 319L and 322, Occupational Health and Safety Amendment (Workplace Exposure Limits) Regulations 2026 (Vic), S.R. No. 165/2026, Safe Work Australia, Model Code of Practice, Safe Work Australia, Workplace Exposure Limits for airborne contaminants and Workplace Health and Safety Queensland, Safe work method statements.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.