How to review a subcontractor's SWMS: a principal contractor's checklist

Last reviewed:

To review a subcontractor's Safe Work Method Statement (SWMS), check that it names the high risk construction work (HRCW), the hazards and risks, the controls, and how those controls will be implemented, monitored and reviewed, for this site.

A principal contractor collects a SWMS from every subcontractor doing high risk construction work. Most of the review is quick if you know what the document has to contain and the signs it was written for a different job. Below is what the regulators say a SWMS must include, a checklist to work through, the reasons a SWMS gets sent back, and how Victoria differs.

You can run the same checks in the free SWMS Review Checklist and export the result as a PDF for your records.

Does a principal contractor have to review a SWMS?

Under the model Work Health and Safety (WHS) Regulations, a principal contractor must take all reasonable steps to obtain a SWMS from any contractor carrying out high risk construction work before that work starts. The principal contractor's WHS management plan must also include arrangements for collecting, assessing, monitoring and reviewing SWMS. Both come from Safe Work Australia's SWMS information sheet.

Under the model WHS Regulations, a construction project is construction work costing $250,000 or more, and each one must have a principal contractor. Thresholds and wording differ between states and territories, so check with your own regulator. Our principal contractor duties by state guide covers the differences.

Who prepares it? Safe Work Australia says the person carrying out the high risk construction work is best placed to prepare the SWMS, in consultation with the workers who will do it. Generally that means the subcontractor prepares it. The principal contractor's job is to check it, then check the work matches it. For who counts as a person conducting a business or undertaking (PCBU), see what is a PCBU.

What must a SWMS contain?

According to the Safe Work Australia information sheet, a SWMS must:

It must also be easily understood by the workers who use it, including workers from non-English speaking backgrounds.

A SWMS only has to cover the high risk construction work. Other hazards on the job still have to be managed, but they do not need to be in the SWMS. The model WHS Regulations list 18 categories of high risk construction work, and our high risk construction work guide lists them.

The SWMS review checklist

Work through these in order. Where the answer is no, write it down and send the SWMS back with the section and the fix needed.

1. Does it cover the right work?

  1. It names the high risk construction work involved, and nothing the subcontractor will do on this job is missing. A roofing SWMS that covers falls but not the mobile crane lifting the sheets is incomplete.
  2. It lists the tasks in a logical sequence of steps.
  3. It matches the scope the subcontractor was engaged to do.

2. Is it written for this job?

  1. It names this project, site or address.
  2. It reflects the actual site conditions, access and surrounding work.
  3. It matches the plant, equipment and materials that will actually be used.
  4. It references the correct legislation and regulator for the state or territory where the work is done.

Safe Work Australia warns that a generic SWMS used at different workplaces may not meet the WHS laws unless it has first been reviewed for the hazards and risks at that workplace and amended as necessary.

3. Do the hazards, risks and controls hold together?

  1. Each high risk task has its hazards, and the risks they create, stated.
  2. Each hazard has a control, and the controls follow the hierarchy of control rather than relying only on personal protective equipment (PPE) and training.
  3. Where one failure would be serious, there is more than one control.
  4. If it uses risk ratings, it shows a rating before and after controls, and any high residual rating is explained.

A SWMS is an administrative control. Safe Work Australia describes it as supporting higher order controls, such as engineering controls, not replacing them.

4. Does it say how the controls will be implemented, monitored and reviewed?

  1. It says who is responsible for putting each control in place.
  2. It says how the controls will be checked on site while the work is under way.
  3. It states what triggers a review, and has space to record changes.

A PCBU must review and, as necessary, revise a SWMS if the control measures are revised. Victoria words its review triggers differently (see below).

5. Who wrote it and who has seen it?

  1. It identifies the business doing the work, with its Australian Business Number (ABN) and a contact.
  2. It names the person who prepared it, and the date.
  3. It shows the workers doing the work were consulted.
  4. It has a sign-on section for the workers on the task.
  5. It records the licences, tickets or competencies the work needs.
  6. It has a visible, current version or revision number.

6. Is the rest of the job covered?

  1. Emergency arrangements, first aid and incident reporting are covered or cross-referenced.
  2. The SWMS will be kept where the work is done, or where it can be delivered quickly. Safe Work Australia says it can also be kept electronically.

Record the outcome

Mark the SWMS as accepted, accepted with conditions, or rejected, and write down what has to change before it comes back. The SWMS Review Checklist has these checks and the outcome boxes, and exports a PDF laid out as form FOR-P07.

A completed review records what you found in the document. It does not assess the work itself, and the business doing the work stays responsible for its own SWMS.

Why do SWMS get sent back?

Nearly always one of these.

After you accept it

Accepting the SWMS is not the end of the principal contractor's part. Safe Work Australia says a principal contractor should have arrangements to make sure the work is done in line with the SWMS, for example by monitoring it on the ground.

If work is not being done in line with the SWMS, it must stop immediately or as soon as it is safe to, and must not start again until it can be done in line with the SWMS.

How long to keep it: the template in the information sheet says a SWMS must be kept and available for inspection until the high risk construction work is finished. If a notifiable incident happens, keep it for at least 2 years from the date of the incident. If the SWMS is revised, keep every version. The subcontractor’s own duties to keep and review it are in keeping, signing and reviewing a SWMS.

How is Victoria different?

Victoria does not use the model WHS laws. It has its own occupational health and safety (OHS) laws, regulated by WorkSafe Victoria, with compliance codes instead of codes of practice. The duty holders are employers and self-employed persons rather than PCBUs. The points below are from WorkSafe Victoria's SWMS page unless noted.

When you run the SWMS Review Checklist, pick Victoria as the state and the wording changes to match.

Sending it back with a better starting point

If a subcontractor's SWMS fails and they need to start again, an editable SWMS written for their trade and state saves them writing from a blank page. They still have to put in the site, the plant, the crew and the controls for this job.

For writing one from scratch, see how to write a SWMS.

Start from a proper SWMS, not a blank page

State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.

This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.