You need a Safe Work Method Statement (SWMS) for demolition work that is high risk construction work (HRCW). Under the model Work Health and Safety (WHS) Regulations, that includes demolition of an element of a structure that is load-bearing or otherwise related to its physical integrity, work that is likely to disturb asbestos, structural alterations that need temporary support, and work where powered mobile plant is moving or a person could fall more than 2 metres.
Victoria is broader. Its list covers construction work "involving demolition", without the load-bearing qualifier. Demolition also comes with its own rules beside the SWMS: notice to the regulator for some jobs, licensing in some states, and asbestos identification before work starts. This guide covers all three.
Is strip-out and demolition construction work?
Construction work includes work carried out in connection with the demolition or dismantling of a structure, and the removal from the workplace of any product or waste resulting from demolition (regulation 289 of the model WHS Regulations; section 289 of Queensland's WHS Regulation 2011). Minor testing, maintenance or repair work on a structure is excluded (r 289(3)(d)), but a strip-out or knock-down is not minor repair work.
Which high risk construction work categories apply?
The model WHS Regulations list 18 categories of high risk construction work in regulation 291 (section 291 in Queensland). The ones demolition work hits most are construction work that:
- involves demolition of an element of a structure that is load-bearing or otherwise related to the physical integrity of the structure
- involves, or is likely to involve, the disturbance of asbestos
- involves structural alterations or repairs that require temporary support to prevent collapse
- involves a risk of a person falling more than 2 metres
- is carried out in an area at a workplace in which there is any movement of powered mobile plant
- is carried out on or near energised electrical installations or services
- is carried out in or near a confined space
- is carried out in an area that may have a contaminated or flammable atmosphere
- involves the use of explosives.
Non-structural strip-out, such as removing linings, ceilings and fixtures, does not fall within the load-bearing category on its own. It often triggers other categories, especially asbestos and falls, and it still has to be managed safely.
Common demolition jobs and the categories they often trigger
This is a guide, not a ruling. The structure, its age, its services and the method decide which categories apply.
| Demolition task | Often triggers | Note |
|---|---|---|
| Structural demolition of walls, slabs or frames | Load-bearing demolition; temporary support; powered mobile plant | An engineered sequence and propping belong in the method. |
| Soft strip-out of linings and fit-out | Possibly asbestos; falls over 2 m | Check the asbestos register or survey before anyone starts. |
| Roof sheet or tile removal | Falls over 2 m; possibly asbestos | Fragile roofs and older sheeting need specific controls. |
| Mechanical demolition with excavators | Powered mobile plant; load-bearing demolition; possibly overhead power lines | Exclusion zones and the sequence of collapse. |
| Removing walls in an occupied home | Temporary support; possibly asbestos; energised electrical services | Services must be isolated and confirmed before work. |
| Cutting or breaking concrete | Load-bearing demolition if structural; powered mobile plant | Silica dust controls sit beside the SWMS. |
| Demolition near pits, tanks or vaults | Confined space; contaminated atmosphere | Entry needs a confined space entry permit. |
What must a demolition SWMS cover?
Regulation 299 of the model WHS Regulations (section 299 in Queensland) says a SWMS must:
- identify the work that is high risk construction work
- state the hazards relating to that work and the risks to health and safety associated with those hazards
- describe the measures to be implemented to control the risks
- describe how the control measures are to be implemented, monitored and reviewed.
It must take into account the circumstances at the workplace and, on a construction project, the principal contractor's WHS management plan. It must be readily accessible and understandable to the people who use it.
For demolition, that usually means the SWMS sets out:
- the structure, the method and the sequence of demolition, and who prepared any engineering advice
- the temporary support or propping, and when it can be removed
- the asbestos register or survey relied on, and what has been removed before work starts
- how electrical, gas and water services were isolated and confirmed
- exclusion zones for falling material and plant, and how the public is protected
- the fall controls for edges, openings and roofs
- how dust is controlled, including silica dust, and the respiratory protective equipment (RPE) used
- how other hazardous materials, such as lead paint, are identified and handled
- who supervises, and how the controls will be checked as the structure changes.
Workplace Health and Safety Queensland (WHSQ) says statements such as "use appropriate PPE" (personal protective equipment) do not detail the control measures. Name the control you will use.
The rules that sit beside the SWMS
Notice to the regulator. Regulation 142 of the model WHS Regulations (section 142 in Queensland) requires a person conducting a business or undertaking (PCBU) to give written notice to the regulator at least 5 days before any of the following demolition work starts:
- demolition of a structure, or a part of a structure that is load-bearing or otherwise related to its physical integrity, that is at least 6 metres high
- demolition work involving load-shifting machinery on a suspended floor
- demolition work involving explosives.
Demolition licences. Some jurisdictions license demolition work under their own regulations. Queensland requires a licence to carry out demolition work (section 143). New South Wales requires a demolition licence for licensed demolition work (section 142A of the Work Health and Safety Regulation 2025 (NSW); licensed demolition work is demolition that must be notified under section 142, or demolition on a chemical installation). Western Australia requires a Class 1 or Class 2 demolition licence for specified kinds of demolition work (Work Health and Safety (General) Regulations 2022 (WA) rr 142B and 142C). South Australia's regulation 143 is a heading only (the note says it is not required in that State), and South Australia instead requires the regulator's approval before certain demolition work starts (regulation 143A). The Northern Territory has the same unused heading (r 143). No equivalent demolition-licence rule was found in the held Victorian, Tasmanian or ACT WHS or OHS Regulations; other laws may still apply. Check what your regulator requires before you quote.
Asbestos before demolition. Regulation 452 (section 452 in Queensland) says the person with management or control of the workplace, or of the structure, must ensure all asbestos likely to be disturbed by the demolition is identified and, so far as is reasonably practicable, removed before the demolition starts. Domestic premises have their own rule (regulation 453). Removal must be done by a licensed asbestos removalist, except for 10 square metres or less of non-friable asbestos and some minor contamination (regulation 458), and the jurisdictions do not all apply that exception the same way. See asbestos removal SWMS and licences.
Safe Work Australia's model Code of Practice: Demolition work is written for people who manage or control a workplace where demolition work is carried out, and people who carry out demolition work. Check with your regulator whether it has legal effect where you work.
Dust, asbestos fibres and the exposure limits change
Demolition can release respirable crystalline silica, asbestos fibres, lead dust and other airborne contaminants. From 1 December 2026, workplace exposure limits (WEL) replace the workplace exposure standards (WES). Safe Work Australia says PCBUs must comply with the WES list up to and including 30 November 2026, and with the WEL list from 1 December 2026. Victoria has made its own amendment regulations, which also commence on 1 December 2026, and some jurisdictions have transition arrangements for particular substances, so check your regulator. Exposure limits are a ceiling, not a target: the duty is still to eliminate or minimise exposure so far as is reasonably practicable. See what are WES and WEL? and what is a silica risk control plan?.
What is in the Demolition pack?
The Demolition SWMS Trade Pack has 21 SWMS: one Demolition Master SWMS and 20 task SWMS:
- Site Establishment & Setout
- Manual Handling
- Material Handling, Loading & Unloading
- Truck Operations & Deliveries
- Soft Demolition - Strip-Out
- Demolition (Structural)
- Electrical Demolition
- Floor Covering Removal
- Roofing Removal
- Cladding Removal - Rope Access
- Cladding Removal - Swing Stage
- Concrete Demolition (Ultra High Pressure Water)
- Mobile Concrete Crusher
- Acrow Props
- Confined Space Work
- Working at Heights - On Structure
- Working Near Overhead Power Lines
- Hazardous Substances
- Working in Private Residences
- Silica Dust
The pack comes in editable Word with a free pack of 29 safe operating procedures (SOPs). Each state edition references that state's Act and regulator. The pack does not replace a licensed asbestos removalist's own documents for licensed removal work.
What still has to be tailored?
Before the SWMS goes to site, add:
- the site, the structure and the demolition method and sequence for this job
- the engineering advice and propping details, if any
- the asbestos register or survey, and what was removed before work started
- confirmation of service isolations
- exclusion zones, hoarding and public protection for this site
- the plant, operators and their licences
- who supervises, and the crew's sign-on after you have talked it through with them.
See how to use a SWMS template and keeping, signing and reviewing a SWMS.
Victoria and other states
Victoria uses the Occupational Health and Safety (OHS) Regulations 2017, made under the OHS Act 2004. Its list of 19 types of high risk construction work includes construction work "involving demolition" and "involving the removal or likely disturbance of asbestos" (regulation 322). Because the demolition item is not limited to load-bearing elements, more strip-out work can need a SWMS in Victoria than elsewhere.
For high risk construction work involving the removal or likely disturbance of asbestos, preparing an asbestos control plan under regulation 272 is taken to be preparing a SWMS, and complying with that plan is taken to be complying with a SWMS for the risk of exposure to airborne asbestos fibres (regulation 327(3)).
The other states and territories have adopted the model WHS Regulations in their own laws, with their own variations such as demolition licensing. See SWMS requirements by state.
Common questions
Does all demolition work need a SWMS?
Under the model WHS Regulations, the demolition category covers demolition of an element of a structure that is load-bearing or otherwise related to its physical integrity. Non-structural strip-out can still need a SWMS if it disturbs asbestos, involves a fall of more than 2 metres or has powered mobile plant moving nearby. In Victoria, construction work involving any demolition is high risk construction work.
Do I need to notify the regulator before demolition?
For some jobs. The model WHS Regulations (regulation 142) require written notice to the regulator at least 5 days before demolition of a load-bearing structure or part at least 6 metres high, demolition involving load-shifting machinery on a suspended floor, or demolition involving explosives.
Do I need a licence to do demolition work?
It depends on the jurisdiction. Queensland, New South Wales and Western Australia license demolition work under their WHS regulations, and South Australia requires the regulator's approval before certain demolition work starts. Asbestos removal has separate licensing rules everywhere. Check with your regulator before you quote.
Does asbestos have to be removed before demolition?
Under the model WHS Regulations (regulation 452), all asbestos likely to be disturbed by the demolition must be identified and, so far as is reasonably practicable, removed before the demolition starts. Domestic premises have their own rule. Licensed removal is required above the thresholds in the regulations.
Does strip-out need a SWMS in Victoria?
Often. Victoria's list includes construction work involving demolition, without limiting it to load-bearing elements, and work involving the removal or likely disturbance of asbestos. Check WorkSafe Victoria's guidance for the work you are doing.
Sources: Work Health and Safety Regulation 2011 (Qld), sections 142, 143, 289, 291, 299, 452, 453 and 458, and the schedule 19 definition of demolition work, Model WHS Regulations numbering, Occupational Health and Safety Regulations 2017 (Vic), Authorised Version No. 018 (as at 20 October 2026), regulations 322 and 327(3), Occupational Health and Safety Amendment (Workplace Exposure Limits) Regulations 2026 (Vic), S.R. No. 165/2026, Safe Work Australia, Model Code of Practice: Demolition work (updated 6 Nov 2026), Safe Work Australia, Workplace Exposure Limits for airborne contaminants and Workplace Health and Safety Queensland, Safe work method statements.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.