Manual handling on its own is not one of the high risk construction work (HRCW) categories, so the law does not require a Safe Work Method Statement (SWMS) just because a job involves lifting or carrying. But hazardous manual tasks must still be managed, and the controls have to follow a set order: get rid of the task or change it before you rely on training and team lifts.
On building sites, manual handling usually shows up inside a SWMS anyway, because the lifting is part of work that is high risk construction work, or because the builder asks every contractor for a manual handling SWMS before starting. This guide covers what the law requires, the controls that work on site, and how to write them so they mean something.
What counts as a hazardous manual task?
Under the model Work Health and Safety (WHS) Regulations, a hazardous manual task is a task that requires a person to lift, lower, push, pull, carry or otherwise move, hold or restrain any person, animal or thing, involving one or more of:
- repetitive or sustained force
- high or sudden force
- repetitive movement
- sustained or awkward posture
- exposure to vibration.
(Definition in the model WHS Regulations; schedule 19 dictionary of Queensland's WHS Regulation 2011.)
Safe Work Australia puts it simply: "Most jobs involve manual tasks, such as lifting, pushing, pulling or carrying. Manual tasks can be hazardous, so you must assess and manage the risks."
On a building site, typical examples are carrying plasterboard, sheet roofing or bags of cement, laying blocks, tying reinforcement bar bent over, overhead drilling, using jackhammers and vibrating plate compactors, and team lifting pipes, beams and windows.
Does manual handling need a SWMS?
Not on its own. A SWMS is required before high risk construction work starts (regulation 299 of the model WHS Regulations; section 299 of Queensland's WHS Regulation 2011). The 18 HRCW categories in regulation 291 cover things like falls of more than 2 metres, trenches deeper than 1.5 metres, powered mobile plant and live traffic. Manual handling is not one of them.
A SWMS will still often cover manual handling when:
- the lifting is part of high risk construction work, for example carrying sheets onto a roof where a person could fall more than 2 metres
- the builder or head contractor requires a manual handling SWMS from every contractor before they start
- your own safety system uses SWMS or job safety analyses (JSAs) to set out controls for all significant tasks.
For the general test, see do I need a SWMS? and high risk construction work: the 18 categories. If a SWMS is not required, a JSA is a common way to set out the controls. See SWMS vs JSA.
What does the law require for manual handling?
Model WHS Regulations. A person conducting a business or undertaking (PCBU) must manage risks to health and safety relating to a musculoskeletal disorder associated with a hazardous manual task (regulation 60; section 60 in Queensland). In choosing controls, the PCBU must have regard to all relevant matters, including:
- postures, movements, forces and vibration
- the duration and frequency of the task
- workplace environmental conditions
- the design of the work area and the layout of the workplace
- the systems of work used
- the nature, size, weight or number of persons, animals or things involved.
The general order of controls in regulation 36 applies: eliminate the risk if you can; if not, minimise it by substitution, isolation or engineering controls, then administrative controls, then personal protective equipment (PPE).
Victoria. The Occupational Health and Safety (OHS) Regulations 2017 deal with hazardous manual handling in Part 3.1. An employer must eliminate the risk of a musculoskeletal disorder so far as is reasonably practicable (regulation 27(1)). If that is not possible, the employer must reduce the risk by altering the workplace layout, the workplace environment or the systems of work, changing the things used, or using mechanical aids (regulation 27(2)). Information, instruction or training can only be relied on solely or primarily if none of those measures is reasonably practicable (regulation 27(4)).
Manual handling controls that work on site
Write the controls in the order the law expects. The higher up the list, the more reliable the control.
1. Get rid of the lift.
- Have materials delivered to the point of use: crane or hoist loads onto the floor or roof they are needed on.
- Order materials pre-cut, pre-assembled or prefabricated so less handling happens on site.
- Plan the site layout so pallets land close to where they will be used.
2. Change the thing being handled.
- Order smaller bags, shorter lengths or lighter blocks where the design allows.
- Choose products with handles or lifting points.
3. Use mechanical aids.
- Trolleys, pallet jacks, panel carts, plasterboard lifters, block lifting clamps, vacuum lifters and material hoists.
- Long-handled tools so workers do not bend to floor level, for example for tying reinforcement bar.
- Low-vibration tools and tool supports for drilling overhead or into concrete.
4. Change the layout, the environment and the system of work.
- Raise work to waist height on trestles or benches.
- Keep access routes clear, level and lit.
- Rotate tasks and build in breaks for repetitive work.
- Plan the work so heavy tasks are not done in the hottest part of the day.
5. Team lifts, information and training.
- Team lifting needs a plan: who lifts, who calls the lift, the route and the set-down point.
- Training in lifting technique supports the controls above. It should not be the only control where a mechanical aid, a different product or a different method is reasonably practicable.
How to write manual handling controls in a SWMS
A SWMS must describe the control measures and how they are to be implemented, monitored and reviewed (regulation 299). Workplace Health and Safety Queensland (WHSQ) says statements such as "use appropriate PPE" do not detail the control measures. The same goes for "use correct lifting technique".
Weak wording and stronger wording:
| Weak | Stronger |
|---|---|
| Use correct lifting technique. | Sheets are lifted to roof level by the delivery crane and set down beside the work area. |
| Team lift heavy items. | Beams over the weight set in the site plan are moved with the panel cart; team lifts use two people with one person calling the lift. |
| Take breaks as needed. | Block laying is rotated with mortar mixing at set points in the shift plan. |
| Use mechanical aids where possible. | Plasterboard lifter on site for all ceiling sheets. |
Name the aid, the delivery method or the work arrangement. If a control depends on equipment, say who provides it.
Reviewing manual handling controls
Under the model WHS Regulations, control measures must be reviewed and, if necessary, revised in the circumstances set out in regulation 38, including when a control does not work, before a change at the workplace, and when a new hazard or risk is found. In Victoria, regulation 28 sets out its own triggers for manual handling, including before a change to the thing, process or system of work, when a musculoskeletal disorder is reported, after a notifiable incident involving manual handling, and on request from a health and safety representative.
If the manual handling controls are inside a SWMS for high risk construction work, the SWMS review rules also apply. See keeping, signing and reviewing a SWMS.
What SWMS Aus has for manual handling
We have a Manual Handling SWMS in 105 trade versions. Each one is written around that trade's work, for example Manual Handling (Carpentry). Each is an editable Word document, and each state version references that state's Act and regulator. The Manual Handling SWMS is also included in the trade packs. Find your trade on the packs page.
If you only need a JSA, the Manual Handling and Team Lifting JSA is a national editable Word document that breaks the job into 7 steps with the hazards and controls for each.
Either way, add your site details, check the controls against the actual job and talk them through with the crew before work starts. See how to use a SWMS template.
Common questions
Is manual handling high risk construction work?
No. Manual handling is not one of the 18 categories of high risk construction work in the model WHS Regulations, or one of Victoria's 19 types. A Safe Work Method Statement (SWMS) is not legally required for manual handling alone, but hazardous manual tasks must still be managed.
Why does the builder want a manual handling SWMS?
Many builders and head contractors ask every contractor for SWMS covering their main tasks, including manual handling, as part of their own site rules. That is a contract or site requirement rather than a legal requirement for a SWMS, but the controls in it still need to be right for the job.
Is training in lifting technique enough?
Usually not. The law expects you to eliminate the task, change it or use mechanical aids first. In Victoria, information, instruction or training can only be relied on solely or primarily if none of the other measures in regulation 27(2) is reasonably practicable.
What is a hazardous manual task?
A task that requires a person to lift, lower, push, pull, carry or otherwise move, hold or restrain any person, animal or thing, involving repetitive or sustained force, high or sudden force, repetitive movement, sustained or awkward posture, or exposure to vibration.
Should I use a SWMS or a JSA for manual handling?
If the manual handling is part of high risk construction work, cover it in that work's SWMS. If it is not, a job safety analysis (JSA) is a common way to set out the steps and controls, unless the builder asks for a SWMS.
Sources: Work Health and Safety Regulation 2011 (Qld), sections 36, 38, 60, 291 and 299 and the schedule 19 definition of hazardous manual task, Model WHS Regulations numbering, Safe Work Australia, Hazardous manual tasks (quote), Safe Work Australia, Model Code of Practice: Hazardous manual tasks, Occupational Health and Safety Regulations 2017 (Vic), Authorised Version No. 018 (as at 20 October 2026), regulations 27 and 28 (Part 3.1) and 322 and Workplace Health and Safety Queensland, Safe work method statements.
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.