A well-written Safe Work Method Statement (SWMS) names the high risk work, the specific hazard, the control that will actually be used, and who puts it in place and checks it. The examples below show common weak wording next to stronger versions for falls, trenches, mobile plant, asbestos, live services and traffic.
Most SWMS that get sent back are not missing a section. They are vague. They say "use appropriate PPE" (personal protective equipment), list five possible controls without choosing one, or describe a job that could be on any site in the country. The regulators have said plainly what they want instead, and it is easier to show than to describe.
For the process of writing one from scratch, see how to write your own SWMS. To check one before it goes to site, use our free SWMS review checklist.
What every SWMS has to say
Under regulation 299 of the model Work Health and Safety (WHS) Regulations (the same number in every state and territory except Victoria), a SWMS must:
- identify the work that is high risk construction work (HRCW)
- state the hazards relating to that work and the risks to health and safety associated with those hazards
- describe the measures to be implemented to control the risks
- describe how the control measures are to be implemented, monitored and reviewed.
It must also be set out and expressed in a way that is readily accessible and understandable to the people who use it.
SafeWork NSW gives a simple example of each part: the high risk work (a risk of a person falling more than two metres), the hazard (working on a roof) and risk (a fall from the roof), the control (roof rails), and how it is implemented and monitored (who arranges the roof rails, who checks they are installed correctly, the job sequence, safe access, supervision and checking of the rails).
What the regulators say good wording looks like
- Name the control. Workplace Health and Safety Queensland (WHSQ) says the SWMS should give clear direction, with no statements that leave a decision to supervisors or workers, and that "use appropriate PPE" does not detail the control measures.
- Choose, do not list. WorkSafe Victoria says listing many risk control options will not properly describe the measures being implemented, and the SWMS should describe the best controls to be implemented.
- Keep it to the high risk work. WorkSafe Victoria says only hazards and risks directly related to the high risk work need to be in a SWMS, and other hazards may be included if it helps, as long as the focus is not lost.
- Leave out what does not help. WorkSafe Victoria suggests not including references to other documents such as Australian Standards, risk matrices and risk scores (which are not legally required), or tasks that are not high risk construction work.
Illustrative examples. The examples below are made up for this guide to show the difference in wording. They are not a SWMS for your job and they do not cover every hazard. Adapt any wording you take from them to your own site, task and conditions.
Illustrative example 1: falls from a roof
High risk construction work: risk of a person falling more than 2 metres. Re-roofing a single-storey house with a 4 metre eave height.
Illustrative example only. Adapt it to your actual job and site; it is not a ready-to-use SWMS.
| Weak | Better |
|---|---|
| Hazard: working at heights. | Hazard: falling from the roof edge, through the old sheeting or skylights, or off the ladder while getting onto the roof. |
| Control: use fall protection as required. Wear harness if needed. | Control: perimeter scaffold with edge protection to all eaves, erected and handed over by the scaffold contractor before roof work starts. Old sheeting confirmed as metal, not asbestos cement, before work starts. Skylights covered with mesh before old sheeting is removed. Roof access by the scaffold stair, not a ladder. |
| Monitoring: supervisor to monitor. | Monitoring: supervisor confirms the scaffold handover tag and skylight covers before the crew goes up. Crew stops and reports if any edge protection is removed or damaged. |
The weak version could be used on any job, and it leaves the decision to the worker. The better version describes this job, says which control was chosen and who checks it.
Illustrative example 2: trench work
High risk construction work: work in or near a trench with an excavated depth greater than 1.5 metres; powered mobile plant.
Illustrative example only. Adapt it to your actual job and site; it is not a ready-to-use SWMS.
| Weak | Better |
|---|---|
| Hazard: trench collapse. | Hazard: trench wall collapse burying a worker; excavator striking workers at the trench edge; spoil falling back into the trench. |
| Control: shore trench as necessary. Keep clear of excavator. | Control: trench shields installed in each section before anyone enters. Underground services located and marked before digging. Spoil kept back from the trench edge by at least [distance set by the engineer or competent person]. Nobody in the trench while the excavator is digging that section. Ladder within the shielded section for access. |
| Monitoring: check regularly. | Monitoring: competent person inspects the trench and shields before each shift, after rain and after anything that could affect the trench walls, and records it. Excavator operator and pit worker agree on the hand signal to stop. |
Illustrative example 3: mobile plant on a busy site
High risk construction work: work in an area with movement of powered mobile plant.
Illustrative example only. Adapt it to your actual job and site; it is not a ready-to-use SWMS.
| Weak | Better |
|---|---|
| Hazard: plant. | Hazard: being struck by the telehandler while it reverses or places loads in the laydown area. |
| Control: be aware of plant. Wear hi-vis. | Control: laydown area fenced with a single gated pedestrian entry. Spotter in place for all reversing in the laydown area. Workers stay outside the fenced area unless the telehandler is stopped with the load lowered and the operator has given the all clear. High-visibility clothing worn. |
| Monitoring: as required. | Monitoring: site supervisor checks the fencing and spotter arrangement before a delivery is unloaded. |
High-visibility clothing is still listed. It is just not the only control.
Illustrative example 4: drilling where asbestos may be present
High risk construction work: work that involves, or is likely to involve, disturbing asbestos.
Illustrative example only. Adapt it to your actual job and site; it is not a ready-to-use SWMS.
| Weak | Better |
|---|---|
| Hazard: asbestos. | Hazard: breathing asbestos fibres released when drilling the eaves lining of a house built before asbestos products were phased out, where the lining has not been tested. |
| Control: take precautions with asbestos. | Control: check the asbestos register or the client's information before work. If unknown, treat as asbestos or have it sampled. Fixing points moved off the lining where the job allows. Others kept out of the work area and a plastic drop sheet laid under the drilling points. Drill only through the lining at the agreed points, using a low-speed drill with shadow vacuuming by an H-class vacuum and wetting the drill point. P2 respirator and disposable coveralls worn. No power sanding, no compressed air. Waste, drop sheets and coveralls bagged, labelled and disposed of as asbestos waste. |
| Monitoring: supervisor to check. | Monitoring: supervisor confirms the asbestos information before work starts and stops the work if suspect material is found outside the agreed points. |
Removal of asbestos is a different job with its own licence rules. See asbestos removal SWMS and licences.
Illustrative example 5: cutting into walls with live wiring
High risk construction work: work on or near energised electrical installations or services.
Illustrative example only. Adapt it to your actual job and site; it is not a ready-to-use SWMS.
| Weak | Better |
|---|---|
| Hazard: electricity. | Hazard: electric shock from cutting or drilling into a wall cavity where live cabling may run. |
| Control: be careful of power. | Control: circuits supplying the work area isolated, locked out, tagged and tested de-energised by the licensed electrician before cutting. Wall scanned before cutting. Cut depth set to the lining thickness. |
| Monitoring: N/A. | Monitoring: electrician confirms isolation and the test result to the leading hand before work starts; lock stays on until the electrician removes it. |
Illustrative example 6: work beside a live road
High risk construction work: work on or adjacent to a road in use by traffic other than pedestrians.
Illustrative example only. Adapt it to your actual job and site; it is not a ready-to-use SWMS.
| Weak | Better |
|---|---|
| Hazard: traffic. | Hazard: workers struck by passing vehicles while unloading on the road verge. |
| Control: follow traffic control. | Control: work done under the approved traffic management for this site, with the lane closure and signs set out by the traffic control contractor before unloading starts. Workers stay inside the delineated work area. Unloading done from the verge side of the truck, not the traffic side. |
| Monitoring: watch traffic. | Monitoring: traffic control contractor confirms the set-up to the supervisor before work starts; work stops if the set-up is disturbed. |
See what is a traffic management plan? for how that plan sits beside the SWMS.
Quick checks before your SWMS goes to site
- Does it name the actual task and site, not just the trade?
- Does it say which high risk construction work categories apply?
- Is every hazard specific to a step in the job?
- Does every control describe something you could check on site?
- Is there one chosen control, not a menu?
- Does it say who puts each control in place and who checks it?
- Is it short enough for the crew to read before they sign?
- Has the crew talked it through?
Where to start
If you would rather not start from a blank page, our SWMS Trade Packs give you the tasks, hazards and controls drafted for your trade and state, in editable Word, so you review and tailor rather than write from scratch. Whatever you start from, the wording has to match the job in front of you. See what to do after you download your SWMS pack.
Common questions
What is an example of a good SWMS control?
A good Safe Work Method Statement (SWMS) control names the actual measure and who is responsible. For example, "perimeter scaffold with edge protection to all eaves, handed over before roof work starts, checked by the supervisor" is a control. "Use fall protection as required" is not, because it leaves the decision to the worker.
Can I write "use appropriate PPE" in a SWMS?
Workplace Health and Safety Queensland says "use appropriate PPE" does not detail the control measures. Name the actual personal protective equipment, such as a P2 respirator or a full-body harness connected to a specified anchor, and make sure PPE is not the only control where higher controls are reasonably practicable.
Should a SWMS include a risk matrix?
It is not required. WorkSafe Victoria says risk matrices and risk scores are not legally required in a SWMS and suggests leaving them out. Some principal contractors still ask for one, so check their requirements.
Should a SWMS cover every hazard on the job?
A SWMS must cover the high risk construction work and its hazards. WorkSafe Victoria says other hazards may be included if it helps, but should not crowd out the high risk work, and they still need to be managed elsewhere.
Are these examples a SWMS I can use?
No. They are illustrative extracts written to show the difference in wording. A SWMS has to be prepared for the actual work, site and crew, and reviewed by a competent person.
Sources: Work Health and Safety Regulation 2011 (Qld), section 299, Safe Work Australia, Model WHS Regulations, SafeWork NSW, Prepare safe work method statement (roof rails example), Workplace Health and Safety Queensland, Safe work method statements and WorkSafe Victoria, Safe work method statements (SWMS).
Start from a proper SWMS, not a blank page
State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.
This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.