A traffic management plan is a written plan for how vehicles, mobile plant and people will move around a worksite without hitting each other: routes, entry and exit points, loading areas, barriers, signs and who is responsible. WHS law requires traffic risks to be managed; it does not name a traffic management plan as a required document in every case. A plan is the usual way to show how you are managing those risks, and principal contractors and clients often ask for one by name.
Safe Work Australia says vehicles, including powered mobile plant, moving in and around a workplace, reversing, loading and unloading are often linked with death and injuries to workers and members of the public. A traffic management plan is how a business shows it has thought that through. This guide covers what goes in one, when it is needed, and how it differs from the traffic control plans used for work on public roads.
What is a traffic management plan?
Safe Work Australia describes a traffic management plan as a plan that outlines how you will manage traffic risks. Traffic means all types of vehicles, including plant, both stationary and moving traffic, pedestrians and cyclists.
Its construction guidance says a traffic management plan documents and helps explain how risks will be managed at the construction workplace, and that a map or sketch of the site and traffic layout helps identify hazards and risks.
When do you need one?
There is no single dollar or size trigger, and no rule that every job must have a document with this name. Look at three things.
1. The duty to manage traffic risks. Every business has to manage risks to health and safety, and that includes traffic. Safe Work Australia says businesses must eliminate traffic risks so far as is reasonably practicable, or minimise them if elimination is not possible. Its general guide says a traffic management plan can help a large workplace with a high volume of traffic communicate how it is managing traffic risks, and its construction guide lists developing and implementing a plan among the key issues to consider. Its online construction duties tool goes further and says "you must prepare a traffic management plan". On a busy site with deliveries, plant and pedestrians, a written plan is the practical way to show how you are meeting the duty.
2. The principal contractor's duties on a construction project. Under the Work Health and Safety (WHS) Regulations, the principal contractor for a construction project must manage risks associated with traffic in the vicinity of the workplace that may be affected by construction work on the project (regulation 315 of the model WHS Regulations; section 315 of Queensland's WHS Regulation 2011). Safe Work Australia's model Code of Practice: Construction work says the WHS management plan may also include information on the development of a construction project traffic management plan.
3. Work on or next to a road. Construction work on, in or adjacent to a road, railway or other traffic corridor in use by traffic other than pedestrians is high risk construction work (HRCW), so it needs a Safe Work Method Statement (SWMS). Safe Work Australia's guidance says that for construction work on or near a public road, the business should also contact the relevant road authority for its traffic management requirements and guidelines and, where relevant, should include that information in the traffic management plan.
And the commercial trigger: many principal contractors, councils and clients ask for a traffic management plan before you start, whatever the size of the job.
What goes in a traffic management plan?
Safe Work Australia's construction traffic guide says a plan may include details of:
- travel paths for vehicles, including entry and exit points and haul routes
- pedestrian and traffic routes
- delivery, loading and unloading areas
- travel paths remote from the workplace, such as turning areas and access ramps
- how often and where vehicles and pedestrians interact
- the traffic control measures for each interaction, including drawings of barriers, walkways and signs
- on a public road, the layout of signs and devices, including temporary speed zones and tapers
- requirements for special vehicles such as large vehicles and mobile cranes
- requirements for loading from the side of the road onto the site.
Safe Work Australia's general guide adds the responsibilities of the people managing traffic, the responsibilities of people expected to interact with it, and instructions for controlling traffic, including in an emergency. It also says the plan should be monitored and reviewed, especially after an incident, and that workers should be familiar with it and trained in its use.
In practice, a good site traffic plan also covers:
- a site map showing all of the above, kept current as the site changes
- delivery times, and who receives and directs deliveries
- spotter and traffic controller arrangements
- parking for workers and visitors
- how the plan is briefed to workers, subcontractors and drivers.
Controls, in order
Safe Work Australia sets out the controls in the usual order:
- Eliminate traffic hazards where you can, for example by removing powered mobile plant and other vehicles from the area.
- Substitute something safer, for example different load-shifting equipment.
- Isolate people from vehicles, for example with physical barriers or separate walkways.
- Engineering controls, such as reversing sensors, rear-view cameras or interlocked gates.
- Administrative controls, such as signs, scheduled delivery times, training and supervision.
- Personal protective equipment, such as high-visibility clothing.
A plan that relies on hi-vis and "watch for vehicles" has skipped most of that list.
Site traffic plan or road traffic control?
These get confused.
- A site traffic management plan covers vehicles, plant and people moving within and in and out of your site.
- Traffic control on a public road, such as a lane closure or a footpath diversion, is set by the road authority's requirements. Safe Work Australia's traffic duties page lists the road authority for each state and territory and refers to the Austroads Guide to Temporary Traffic Management and Australian Standard (AS) 1742, Manual of uniform traffic control devices.
If your job affects a public road or footpath, contact the road authority or council first. Some states also have specific rules. For example, section 315M of Queensland's WHS Regulation 2011 says that if an adjoining area is to be closed, the principal contractor must get written approval from the authority or person that controls the area before construction work starts, and use any closure measures the authority requires.
How does it fit with the SWMS and the WHS management plan?
- The WHS management plan is the principal contractor's plan for the whole project. It may also include information on the development of a construction project traffic management plan.
- The traffic management plan sets the routes, zones and controls for traffic across the site.
- The SWMS covers a specific high risk task, such as work beside a live road or in an area with moving plant, and should be consistent with the traffic plan.
If the SWMS says plant is separated from workers by a fenced laydown area, the traffic plan map should show that fence.
Our Traffic, Parking and Pedestrian Management Plan
Our Traffic, Parking and Pedestrian Management Plan is a stand-alone template for managing traffic, parking and pedestrians on a project. It has 11 sections (from project details, legislation and responsibilities through to planning and site establishment, controls during construction, a traffic management map, monitoring and sign-off) and 6 forms and records, including a traffic management map, delivery schedule, traffic and pedestrian check, plan briefing record, vehicle entry and delivery flowchart and completion checklist. It comes in editable Word, with editions for each state.
It is a site plan. It does not replace the traffic control plans a road authority or council requires for work on a public road, and it needs the project detail completed by a competent person before use. For other project plans, see all management plans.
Common questions
What is a traffic management plan in construction?
A traffic management plan is a written plan setting out how vehicles, powered mobile plant and pedestrians will be managed on a construction site, including routes, entry and exit points, loading areas, barriers, signs, responsibilities and how the plan is monitored and reviewed.
Is a traffic management plan a legal requirement?
Businesses must manage traffic risks under work health and safety (WHS) law, so far as is reasonably practicable, and on a construction project the principal contractor must manage traffic risks in the vicinity of the workplace. The law does not require a document called a traffic management plan in every case, but Safe Work Australia's guidance says a plan can help, and principal contractors and clients commonly require one by name.
Who prepares a traffic management plan?
On a construction project, the principal contractor usually prepares the site traffic management plan as part of managing the project. Subcontractors may be asked to prepare one for their own work area or deliveries. Traffic control on a public road follows the road authority's requirements, including who may design and set it up.
Do I need a SWMS for work next to a road?
Yes. Construction work on or next to a road, railway or other traffic corridor in use by traffic other than pedestrians is high risk construction work, so a Safe Work Method Statement (SWMS) is required before it starts.
What is the difference between a traffic management plan and a traffic guidance scheme?
A site traffic management plan covers traffic within and around your worksite. A traffic guidance scheme is the arrangement of temporary signs and devices used to warn and guide traffic around, through or past work on a public road, prepared to the road authority's requirements (Austroads Guide to Temporary Traffic Management, Part 2). Some road authorities still call this a traffic control plan.
Sources: Safe Work Australia, Traffic management (construction duties tool), Safe Work Australia, Traffic management guide, Safe Work Australia, General guide for workplace traffic management (July 2014), Safe Work Australia, Model Code of Practice, Work Health and Safety Regulation 2011 (Qld), sections 291, 315 and 315M and Austroads, Guide to Temporary Traffic Management Part 2.
Start from a proper SWMS, not a blank page