Master SWMS vs task SWMS: how to use both on site

Last reviewed:

A master Safe Work Method Statement (SWMS) covers a whole trade's high risk work at a general level. A task SWMS covers one specific job, such as installing roof trusses, in more detail. Use the master SWMS as the base for the trade and a task SWMS for the higher risk jobs, and review both against the actual site before work starts.

"Master SWMS" is not a term in the legislation. Regulators talk about "generic" SWMS, and they accept them on one condition: that they are reviewed and made to fit the actual work and site before the high risk work starts. This guide explains the difference, what the regulators say, and a practical way to use both.

What is a master SWMS?

A master SWMS is an overarching SWMS for a trade. It covers the main high risk construction work (HRCW) the trade carries out, the key hazards and the controls, from set-up to pack-up. On our site, each trade's Master SWMS is described as the overarching SWMS for all of that trade's work where a dedicated task SWMS is not in place. For example, the Carpentry Master SWMS is aimed at controlling falls over 2 metres, truss and frame collapse, power tool and nail gun injury, and wood dust and silica across framing, trusses, lock-up and fix-out, cladding, decking, stairs, handrails and cabinetry.

Its strength is breadth. One document covers the trade's common work, and the crew gets one consistent set of controls.

Its weakness is depth. A document that covers everything a carpenter might do cannot describe the exact sequence for craning trusses onto a two-storey frame.

What is a task SWMS?

A task SWMS covers one activity in detail: the steps, the hazards at each step, the controls and who checks them. Examples are "Framing & Trusses", "Painting Asbestos Roofs" or "Retaining Walls". Because it is narrower, it can be specific about the method, plant, sequence and checks for that job.

What do the regulators say?

None of the regulators use the word "master", but they do discuss generic SWMS and SWMS covering more than one activity.

The legal content test is the same either way. Under regulation 299 of the model Work Health and Safety (WHS) Regulations (section 299 of Queensland's WHS Regulation 2011), every SWMS must identify the high risk work, state the hazards and risks, describe the controls, and describe how the controls are implemented, monitored and reviewed, taking into account the circumstances at the workplace.

Master or task: side by side

Master or task: side by side
Master SWMSTask SWMS
CoversThe trade's common high risk workOne specific activity
Level of detailGeneral: key hazards and controls across the tradeSpecific: steps, sequence, plant and checks for one job
Best forRoutine work across many sites; a base for the tradeHigher risk or complex jobs; jobs with their own method
Main riskToo broad to show how a specific job is controlledMissing interactions with other work on the same site
Still needsSite review, with irrelevant content removedSite review, and coordination with other SWMS on site

How to use both on site

  1. Start with the job list. Write down the tasks you will do on this site and mark which are high risk construction work. See high risk construction work: the 18 categories.
  2. Use the master SWMS for the trade's routine work. Review it against the site, add the site details, and remove sections that do not apply.
  3. Add a task SWMS where the job needs it. If a task has its own method, plant or sequence (for example craned trusses, painting an asbestos roof, or a retaining wall beside an excavation), use the task SWMS for it.
  4. Check they do not contradict each other. If the master says one access method and the task SWMS says another, fix it before work starts.
  5. Give the principal contractor what applies. On a construction project, a copy of the SWMS must be given to the principal contractor before the high risk work starts (section 301 in Queensland). Send what covers this job, not everything you own.
  6. Talk it through with the crew. Go through the master and any task SWMS that apply, then get the crew to sign on.
  7. Review when things change. A SWMS must be reviewed and, as necessary, revised if the relevant controls are revised. WorkSafe Victoria adds review whenever the high risk work changes, if there is a sign the controls are not working, and after any incident during the work.

An illustrative example

Illustrative example. This is a made-up job used to show the method. Adapt it to your own site, task and conditions.

A carpentry business is engaged to frame and fix out a two-storey house. On this job the crew will stand frames, install craned roof trusses, fit a stair and balustrades, and do lock-up and fix-out.

The builder receives the reviewed master SWMS and the two task SWMS, the crew is taken through them before work starts, and they are reviewed if the method changes, for example if the trusses end up being lifted with a different crane or from a different position.

Common mistakes

What is in our Trade Packs?

Every SWMS Trade Pack includes a Master SWMS for the trade alongside the task SWMS. For example, the Carpentry pack has 18 SWMS (one Master SWMS and 17 task SWMS), the Painting pack has 17 (one Master and 16 task) and the Bricklaying pack has 13 (one Master and 12 task). They come in editable Word, written for your state, with the trade's safe operating procedures (SOPs) included. Each one still needs to be reviewed against the actual site by a competent person before use.

See which SWMS pack do I need? and what to do after you download your SWMS pack.

Common questions

What is a master SWMS?

A master Safe Work Method Statement (SWMS) is an overarching SWMS covering a whole trade's common high risk construction work at a general level. It is used as a base for the trade, with task SWMS for jobs that need more detail. It still has to be reviewed against the actual site before work starts.

Is a generic or master SWMS legal?

Regulators accept generic SWMS if they are reviewed and revised to fit the actual high risk work and workplace before the work starts. WorkSafe Victoria adds that content not relevant to the site should be removed.

Can one SWMS cover several high risk activities?

Yes. Workplace Health and Safety Queensland says one SWMS can cover all the high risk construction work at a workplace, or separate SWMS can be prepared for each type. If you use separate ones, check how the activities affect each other.

Should I give the principal contractor my master SWMS or my task SWMS?

Give the SWMS that covers the high risk work you will do on that job. For routine trade work that may be the reviewed master SWMS; for higher risk or complex tasks, add the task SWMS for that job.

How many SWMS should I bring to a site induction?

Only what is needed for the high risk work you will do there. WorkSafe Victoria says the number of SWMS presented at a site induction should be kept to what is necessary.

Sources: Workplace Health and Safety Queensland, Safe work method statements, SafeWork NSW, Prepare safe work method statement (using a generic SWMS), WorkSafe Victoria, Safe work method statements (SWMS) and Work Health and Safety Regulation 2011 (Qld), sections 299, 301 and 302.

Start from a proper SWMS, not a blank page

State-specific, editable templates written for your state. Download instantly, then make it yours for the job and the site.

This guide is general information, not legal or safety advice, and does not guarantee compliance. Laws and site conditions vary, so always check your state regulator and have documents reviewed by a competent person.